2808 E CINCINNATI ST 90033

Certificate Information: 2808 E CINCINNATI ST 90033

Application / Permit
20014-10000-04610
Plan Check / Job No.
B20LA19526
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 593.7 SF. TO THE REAR OF THE EXISTING SINGLE FAM. DWELLING .
Permit Issued
Issued on 3/23/2023
Issuing Office
Metro
Current Status
Issued on 3/23/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 STANLEY RAAP
Corrections Issued 11/12/2020 STANLEY RAAP
Building Plans Picked Up 11/20/2020 APPLICANT
Applicant returned to address corrections 2/24/2023 FERNANDO FLORES
Plan Check Approved 3/22/2023 KHUONG TRUONG
Issued 3/23/2023 APPLICANT

Permit Application Clearance Information

Permit Cleared 9/2/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/9/2021 THOMAS LANG
Sewer availability Cleared 1/12/2022 JEANIE LAM
Low Impact Development Cleared 8/15/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/26/2022 JEANIE LAM
Grading Pre-Inspection Cleared 10/3/2022 KIRK LINKLATER
GPI Written Notices Cleared 3/22/2023 STANLEY RAAP

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2023 Corrections Issued OSVALDO PARAMO
METHANE-Barrier 7/14/2023 Approved OSVALDO PARAMO
METHANE-Subgrade 7/14/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 8/10/2023 Not Ready for Inspection SCOTT FINNILA
Footing/Foundation/Slab 8/11/2023 Conditional Approval SCOTT FINNILA
PLUMBING-Rough 12/1/2023 Corrections Issued ALIZAH MAYAGOITIA
Shower Pan 12/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 12/7/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 2/21/2024 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 2/21/2024 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 2/21/2024 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 6/25/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/2/2024 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 10/2/2024 Approved LUIS CASTRO
Green Building Rough 10/2/2024 Approved LUIS CASTRO
Insulation 10/2/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 10/2/2024 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Approved JOHN QUINTANILLA
Insulation 10/10/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 10/16/2024 Approved OSVALDO PARAMO
Drywall Nailing 10/16/2024 Approved OSVALDO PARAMO
METHANE-Rough 10/16/2024 Approved OSVALDO PARAMO
ELECTRICAL-Final 11/21/2024 Corrections Issued WILLIAM SIERRA