6156 N DENNY AVE 91606
Certificate Information: 6156 N DENNY AVE 91606
- Application / Permit
- 20014-10000-04609
- Plan Check / Job No.
- B20LA19519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADDITION TO (E) DETACHED GARAGE.
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2020 | TSE MING HUANG |
| Corrections Issued | 10/31/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 3/17/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 5/14/2021 | TSE MING HUANG |
| Plan Check Approved | 6/23/2021 | FERNANDO FLORES |
| Issued | 6/25/2021 | APPLICANT |
| Building Plans Picked Up | 6/28/2021 | APPLICANT |
| CofO in Progress | 11/9/2021 | ARAM AVEDISIAN |
| CofO Issued | 8/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 12/4/2020 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 3/6/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2021 | Approved | DANIEL DREW |
| Reinforced Concrete Frame | 8/10/2021 | Not Ready for Inspection | DANIEL DREW |
| Underground Mechanical | 8/10/2021 | Partial Approval | DANIEL DREW |
| Footing/Foundation/Slab | 8/13/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 9/3/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/3/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/10/2021 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/10/2021 | Approved | LILIANA PORTILLO |
| Green Building Rough | 9/10/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/10/2021 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/1/2021 | Approved | DANIEL DREW |
| Final | 11/1/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 11/1/2021 | Approved | DANIEL DREW |
| Smoke Detectors | 11/1/2021 | Approved | DANIEL DREW |
| Final | 11/9/2021 | OK to Issue CofO | ARAM AVEDISIAN |