6156 N DENNY AVE 91606

Certificate Information: 6156 N DENNY AVE 91606

Application / Permit
20014-10000-04609
Plan Check / Job No.
B20LA19519
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION TO (E) DETACHED GARAGE.
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 8/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 10/30/2020 TSE MING HUANG
Corrections Issued 10/31/2020 TSE MING HUANG
Applicant returned to address corrections 3/17/2021 RAHEL BEYENE
Applicant returned to address corrections 5/14/2021 TSE MING HUANG
Plan Check Approved 6/23/2021 FERNANDO FLORES
Issued 6/25/2021 APPLICANT
Building Plans Picked Up 6/28/2021 APPLICANT
CofO in Progress 11/9/2021 ARAM AVEDISIAN
CofO Issued 8/15/2022 DANIEL ORRANTE
Permit Finaled 8/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/4/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 12/4/2020 GABRIEL ROBLES
Construction near power lines Cleared 3/6/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/4/2021 Approved DANIEL DREW
Reinforced Concrete Frame 8/10/2021 Not Ready for Inspection DANIEL DREW
Underground Mechanical 8/10/2021 Partial Approval DANIEL DREW
Footing/Foundation/Slab 8/13/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Approved DANIEL DREW
ELECTRICAL-Rough 9/3/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 9/3/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/10/2021 Approved LILIANA PORTILLO
Drywall Nailing 9/10/2021 Approved LILIANA PORTILLO
Green Building Rough 9/10/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/10/2021 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/1/2021 Approved DANIEL DREW
Final 11/1/2021 Corrections Issued DANIEL DREW
Green Building Final 11/1/2021 Approved DANIEL DREW
Smoke Detectors 11/1/2021 Approved DANIEL DREW
Final 11/9/2021 OK to Issue CofO ARAM AVEDISIAN