3509 S SYCAMORE AVE 90016
Certificate Information: 3509 S SYCAMORE AVE 90016
- Application / Permit
- 20014-10000-04607
- Plan Check / Job No.
- B20LA19501
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEER DESIGN.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 3/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2020 | ZAW HAN |
| Corrections Issued | 11/25/2020 | ZAW HAN |
| Plan Check Approved | 12/22/2020 | GEORGE ALVAREZ |
| Issued | 1/11/2021 | APPLICANT |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| CofO in Progress | 5/18/2022 | JOSE AVILA |
| Permit Finaled | 3/8/2023 | DANIEL ORRANTE |
| CofO Issued | 3/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 12/11/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/14/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Rank-1 Construction Co; Lic. No.: 960933-B | 1698 BRIDGEPORT AVENUE CLAREMONT, CA 91711 |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 1/27/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 4/27/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 5/19/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 6/21/2021 | Partial Approval | STUART CHAPMAN |
| Sewer | 6/21/2021 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 6/21/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/25/2021 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/25/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/25/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 6/25/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/23/2021 | Partial Approval | JESUS PINEDA |
| Insulation | 8/9/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/25/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/25/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/25/2021 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/22/2021 | Partial Approval | MASHEL JONGERT |
| Gas Test | 11/17/2021 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Not Ready | JOSE AVILA |
| ELECTRICAL-Final | 12/8/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 12/8/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/8/2021 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 12/16/2021 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 12/16/2021 | Approved | JOSE AVILA |
| Final | 12/16/2021 | Corrections Issued | JOSE AVILA |
| Green Building Final | 12/16/2021 | Approved | JOSE AVILA |
| HVAC-Final | 12/16/2021 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/16/2021 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/16/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/27/2022 | Approved | JOSE AVILA |
| Final | 1/27/2022 | Corrections Issued | JOSE AVILA |
| Final | 5/17/2022 | OK to Issue CofO | JOSE AVILA |