740 N JUNE ST 90038

Certificate Information: 740 N JUNE ST 90038

Application / Permit
20014-10000-04606
Plan Check / Job No.
B20LA19500
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE (216 S.F.) TO ADD + 1 STORY ADDITION (275 S.F.), TOTAL ADU AREA = 491 S.F.
Permit Issued
Issued on 4/23/2021
Issuing Office
Current Status
CofO Issued on 2/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 11/4/2020 RAHEL BEYENE
Corrections Issued 11/25/2020 RAHEL BEYENE
Plan Check Approved 3/24/2021 ADAM HEGAZI
Issued 4/23/2021 APPLICANT
Building Plans Picked Up 5/3/2021 APPLICANT
CofO in Progress 2/10/2023 JOAQUIN GREENOUGH
Permit Finaled 2/23/2023 DEROLD HAUFF
CofO Issued 2/23/2023 DEROLD HAUFF
Permit Finaled 2/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/8/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 1/8/2021 JEANIE LAM
Sewer availability Cleared 1/8/2021 JEANIE LAM
Construction near power lines Cleared 2/10/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 3/3/2021 JOHN CONNEALLY

Contact Information

Contractor Uribe Miguel; Lic. No.: 902301-B 645 W FLORAL DR      MONTEREY PARK, CA 91754
Engineer Vega,, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/23/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 6/30/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 7/26/2021 Approved RAUL BARAJAS
METHANE-Barrier 7/26/2021 Approved RAUL BARAJAS
METHANE-Subgrade 7/26/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 3/9/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 3/9/2022 Corrections Issued SCOTT FINNILA
Green Building Rough 3/9/2022 Corrections Issued SCOTT FINNILA
HVAC-Rough 3/9/2022 Corrections Issued SCOTT FINNILA
METHANE-Rough 3/9/2022 Approved SCOTT FINNILA
PLUMBING-Rough 3/9/2022 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 3/30/2022 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 4/29/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 5/17/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 5/17/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 5/17/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 5/17/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 5/17/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/21/2022 Conditional Approval BRIAN SULLIVAN
Gas Test 6/21/2022 Corrections Issued BRIAN SULLIVAN
Green Building Rough 6/21/2022 Approved BRIAN SULLIVAN
HVAC-Rough 6/21/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/21/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 6/21/2022 Partial Approval BRIAN SULLIVAN
Insulation 6/27/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/27/2022 Partial Approval RYAN SALAZAR
PLUMBING-Rough 6/27/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/8/2022 Approved BRIAN SULLIVAN
Shower Pan 7/8/2022 Approved BRIAN SULLIVAN
Drywall Nailing 8/9/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/9/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 1/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 1/6/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 1/6/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 1/6/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/18/2023 Approved JOAQUIN GREENOUGH
Final 1/18/2023 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 1/18/2023 Approved JOAQUIN GREENOUGH
Final 1/19/2023 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Final 2/6/2023 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Approved JOAQUIN GREENOUGH
Final 2/8/2023 OK to Issue CofO JOAQUIN GREENOUGH