4007 S HEPBURN AVE 90008
Certificate Information: 4007 S HEPBURN AVE 90008
- Application / Permit
- 20014-10000-04605
- Plan Check / Job No.
- B20LA19484
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO EXISTING 2 STORY SFD
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- Issued on 5/25/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 12/10/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/21/2020 | WING SUEN |
| Applicant returned to address corrections | 2/2/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/4/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 4/16/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/6/2021 | CRYSTEL MAALOUF |
| Issued | 5/25/2021 | APPLICANT |
| Building Plans Picked Up | 5/27/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 1/21/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 1/26/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2021 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 9/15/2021 | Conditional Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 1/18/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/24/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 1/24/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/24/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 1/24/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/14/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 4/14/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | ANTHONY EGSON |
| Pre-Inspection | 5/27/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/30/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 7/13/2022 | Approved | ANTHONY EGSON |
| Insulation | 4/19/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/11/2023 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 3/22/2024 | Approved | ANTHONY EGSON |