3152 S PURDUE AVE 90066
Certificate Information: 3152 S PURDUE AVE 90066
- Application / Permit
- 20014-10000-04598
- Plan Check / Job No.
- B20LA19452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATION AND ADDITION TO 1-STORY SFD.
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/5/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 12/29/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 3/3/2021 | RICARDO RAMIREZ |
| Issued | 3/5/2021 | APPLICANT |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| CofO in Progress | 8/30/2022 | KENNETH NAGLE |
| Permit Finaled | 8/31/2022 | DANIEL ORRANTE |
| CofO Issued | 8/31/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/31/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/5/2021 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 2/18/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | DINAH GARIN |
Contact Information
| Contractor | Intension Construction Inc; Lic. No.: 956850-B | 1378 CARMONA AVE LOS ANGELES, CA 90019 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/17/2021 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 6/17/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2021 | Partial Approval | OGANES TARAKHCHYAN |
| MERV13>=Rough | 6/25/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 7/30/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 8/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| MERV13>=Rough | 8/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/3/2021 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/7/2021 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 9/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pre-Inspection | 9/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/17/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/17/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/24/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/24/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 9/24/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| MERV13>=Rough | 9/29/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/1/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 10/29/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 10/29/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 11/9/2021 | Conditional Approval | JOHNNY MIRANDA |
| Shower Pan | 11/9/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/16/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 11/24/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/24/2021 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/21/2022 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 3/21/2022 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/12/2022 | Approved | JOHNNY MIRANDA |
| MERV13>=Rough | 5/12/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 6/6/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 6/6/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 6/6/2022 | Approved | JOHNNY MIRANDA |
| Final | 6/16/2022 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Final | 6/16/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 6/16/2022 | Approved | JOHNNY MIRANDA |
| Final | 8/16/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 8/22/2022 | Conditional Approval | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | JOHNNY MIRANDA |