8219 S GULANA AVE 90293
Certificate Information: 8219 S GULANA AVE 90293
- Application / Permit
- 20014-10000-04593
- Plan Check / Job No.
- B20LA19434
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND FLOOR ADDITION TO (E) 2-STORY SFD. INT. & EXT. STRUCTURAL REMODEL PER PROVIDED IN THE PLAN.
- Permit Issued
- Issued on 11/19/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/3/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/18/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| Plan Check Approved | 7/26/2021 | MAHNAZ NOURHASHEMI |
| Issued | 11/19/2021 | APPLICANT |
| CofO in Progress | 9/27/2022 | BOBBY KEY |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/24/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 6/14/2021 | MAHNAZ NOURHASHEMI |
| GPI Written Notices | Cleared | 7/26/2021 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Mendoza,, Fabian; Lic. No.: C90183 | PO BOX 2305 NORWALK, CA 90651 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/18/2022 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/20/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/22/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 4/22/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 5/5/2022 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 5/5/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/5/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | BOBBY KEY |
| Green Building Rough | 5/10/2022 | Approved | BOBBY KEY |
| Insulation | 5/10/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 5/17/2022 | Approved | BOBBY KEY |
| Final | 5/17/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 9/21/2022 | Approved | BOBBY KEY |
| Final | 9/21/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 9/21/2022 | Approved | BOBBY KEY |
| HVAC-Final | 9/21/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 9/21/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 9/21/2022 | Approved | BOBBY KEY |
| Final | 9/27/2022 | OK to Issue CofO | BOBBY KEY |