8418 S CAMPION DR 90045
Certificate Information: 8418 S CAMPION DR 90045
- Application / Permit
- 20014-10000-04585
- Plan Check / Job No.
- B20LA19399
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO DETACHED ADU AND ADDITION (2 STORY) PER ORDINANCE
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | CARLOS MONTES |
| Corrections Issued | 11/18/2020 | CARLOS MONTES |
| Quality Review Completed | 12/7/2020 | WING SUEN |
| Applicant returned to address corrections | 1/15/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 7/22/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 7/30/2021 | CARLOS MONTES |
| Plan Check Approved | 9/16/2021 | CARLOS MONTES |
| Issued | 10/29/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| CofO in Progress | 2/1/2023 | BOBBY KEY |
| Permit Finaled | 2/7/2023 | DANIEL ORRANTE |
| CofO Issued | 2/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2021 | NIKTA MOUSAVI |
| Specific Plan | Cleared | 2/10/2021 | PEDRO AYALA |
| Low Impact Development | Cleared | 5/13/2021 | JORGE MEJIA LEMUS |
| Sewer availability | Cleared | 6/3/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/1/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/7/2022 | Conditional Approval | BOBBY KEY |
| METHANE-Subgrade | 7/7/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/7/2022 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 7/7/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/8/2022 | Approved | BOBBY KEY |
| METHANE-Barrier | 7/8/2022 | Approved | BOBBY KEY |
| METHANE-Subgrade | 7/8/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 8/26/2022 | Corrections Issued | BOBBY KEY |
| Deputy Wood Construction | 8/31/2022 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 9/9/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 9/9/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Approved | BOBBY KEY |
| METHANE-Rough | 9/9/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/9/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 9/28/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 9/28/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/3/2022 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 10/3/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/7/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 10/7/2022 | Approved | BOBBY KEY |
| Insulation | 10/7/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 10/7/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/12/2022 | Approved | BOBBY KEY |
| Insulation | 10/12/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/12/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 10/19/2022 | Conditional Approval | RICHARD STEINBACH |
| Drywall Nailing | 12/23/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 12/23/2022 | Corrections Issued | EVAN COOPER |
| Final | 12/23/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/23/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 12/23/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 12/23/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 12/28/2022 | Not Ready for Inspection | BOBBY KEY |
| Final | 12/28/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 12/28/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 12/28/2022 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 1/9/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/9/2023 | Approved | BOBBY KEY |
| Final | 1/9/2023 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 1/9/2023 | Approved | BOBBY KEY |
| HVAC-Final | 1/9/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 1/9/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 1/9/2023 | Approved | BOBBY KEY |
| Final | 2/1/2023 | OK to Issue CofO | BOBBY KEY |
| Service/Power Release | 2/1/2023 | Approved | BOBBY KEY |