2412 W RESERVOIR ST 90026

Certificate Information: 2412 W RESERVOIR ST 90026

Application / Permit
20014-10000-04580
Plan Check / Job No.
B20LA19370
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TWO-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING, TO CREATE 2 BEDROOMS, ONE BATHROOM AND DECK.
Permit Issued
Issued on 5/31/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 JOHNNY WU
Corrections Issued 12/4/2020 JOHNNY WU
Quality Review Completed 12/8/2020 TIEN JEN WANG
Building Plans Picked Up 12/15/2020 APPLICANT
Applicant returned to address corrections 6/24/2021 JOHNNY WU
Applicant returned to address corrections 9/23/2021 JOHNNY WU
Applicant returned to address corrections 9/24/2021 JOHNNY WU
Applicant returned to address corrections 10/20/2021 JOHNNY WU
Applicant returned to address corrections 5/6/2022 JOHNNY WU
Applicant returned to address corrections 5/25/2022 JOHNNY WU
Plan Check Approved 5/25/2022 JOHNNY WU
Issued 5/31/2022 APPLICANT
CofO in Progress 5/11/2026 HAMIK HARTOUNIAN
CofO Issued 5/13/2026 DEROLD HAUFF
Permit Finaled 5/13/2026 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 6/24/2021 JOHNNY WU
Grading Pre-Inspection Cleared 6/24/2021 JOHNNY WU
Green Code Cleared 6/24/2021 JOHNNY WU
Sewer availability Cleared 2/1/2022 ABEL CASILLAS
Miscellaneous Cleared 5/6/2022 JOHNNY WU
Eng Process Fee Ord 176,300 Cleared 5/23/2022 ABEL CASILLAS
Low Impact Development Cleared 5/23/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/23/2022 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Beck,, Charles Joseph; Lic. No.: C19289 129 WEST PONDERA STREET      LANCASTER, CA 93534
Engineer Duke,, Ryan Daniel; Lic. No.: C79729 30230 HART OAKS DR      KEENE, CA 93531

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2022 Partial Inspection THOMAS LOGRASSO
Piling/Pier/Caisson 9/11/2023 Not Ready for Inspection THOMAS LOGRASSO
Deputy Reinf. Concrete 9/14/2023 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 9/18/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/18/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Barrier 9/18/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Subgrade 9/18/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Piling/Pier/Caisson 9/18/2023 Corrections Issued ALIZAH MAYAGOITIA
Piling/Pier/Caisson 9/20/2023 Corrections Issued THOMAS LOGRASSO
Deputy Reinf. Concrete 9/21/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 11/20/2023 Not Ready for Inspection THOMAS LOGRASSO
Piling/Pier/Caisson 11/20/2023 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 12/4/2023 Partial Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 12/14/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 12/14/2023 Approved THOMAS LOGRASSO
Deputy Reinf. Concrete 12/18/2023 Conditional Approval THOMAS LOGRASSO
Deputy Wood Construction 1/5/2024 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 7/3/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/3/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/17/2024 Approved ENRIQUE MIRELES
HVAC-Rough 7/17/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/8/2024 Approved HAMIK HARTOUNIAN
Green Building Rough 8/8/2024 Approved HAMIK HARTOUNIAN
Insulation 8/8/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/8/2024 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Rough 8/8/2024 Approved HAMIK HARTOUNIAN
Shower Pan 8/8/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 8/8/2024 Approved HAMIK HARTOUNIAN
Insulation 8/13/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/13/2024 Partial Approval HAMIK HARTOUNIAN
Shower Pan 8/13/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 9/9/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 9/9/2024 Approved LUIS CASTRO
ELECTRICAL-Final 7/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Final 7/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 7/17/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 7/17/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 7/17/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 7/17/2025 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 7/17/2025 Partial Inspection OSVALDO PARAMO
Final 10/28/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 10/28/2025 Approved HAMIK HARTOUNIAN
Smoke Detectors 10/28/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Final 4/17/2026 Corrections Issued HAMIK HARTOUNIAN
Smoke Detectors 4/17/2026 Approved HAMIK HARTOUNIAN
Final 5/7/2026 Partial Inspection HAMIK HARTOUNIAN
Deputy Reinf. Concrete 5/11/2026 Conditional Approval HAMIK HARTOUNIAN
Final 5/11/2026 OK to Issue CofO HAMIK HARTOUNIAN