12953 N GLADSTONE AVE 91342
Certificate Information: 12953 N GLADSTONE AVE 91342
- Application / Permit
- 20014-10000-04579
- Plan Check / Job No.
- B20LA19368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 8/24/2021
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | DANIEL YIP |
| Corrections Issued | 12/1/2020 | DANIEL YIP |
| Quality Review Completed | 12/2/2020 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 4/5/2021 | DANIEL YIP |
| Plan Check Approved | 6/1/2021 | DANIEL YIP |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Issued | 8/24/2021 | APPLICANT |
| CofO in Progress | 11/30/2023 | KEVIN BERBERYAN |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 1/22/2021 | PATRICK MISCHLICH |
| Private sewage disp. approval | Cleared | 2/18/2021 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/10/2021 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 4/5/2021 | DANIEL YIP |
Contact Information
| Contractor | F & G Builders Inc; Lic. No.: 1014017-B | 12953 GLADSTONE AVE SYLMAR, CA 91342 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/18/2022 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 8/5/2022 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/14/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/6/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 4/6/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| MERV13>=Rough | 4/6/2023 | Approved | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 4/6/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/12/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/12/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/12/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/12/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/25/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 4/25/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/25/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 4/27/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/27/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/17/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 5/17/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 6/22/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 6/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 6/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 9/11/2023 | Not Ready for Inspection | ROBERT GOLD |
| Final | 9/11/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 9/11/2023 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Final | 9/11/2023 | Not Ready for Inspection | ROBERT GOLD |
| MERV13>=Final | 9/11/2023 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Final | 9/11/2023 | Not Ready for Inspection | ROBERT GOLD |
| Smoke Detectors | 9/11/2023 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 9/20/2023 | Approved | KEVIN BERBERYAN |
| Final | 9/20/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/20/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 9/20/2023 | Approved | KEVIN BERBERYAN |
| MERV13>=Final | 9/20/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 9/20/2023 | Approved | KEVIN BERBERYAN |
| Final | 11/30/2023 | OK to Issue CofO | KEVIN BERBERYAN |