12508 W ROSE AVE 90066

Certificate Information: 12508 W ROSE AVE 90066

Application / Permit
20014-10000-04578
Plan Check / Job No.
B20LA19360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE (20ft x 20ft) TO ADU WITH ADDITION (12.5ft x 11.5ft).
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 11/4/2020 FARSHAD ALIMOHAMADI
Corrections Issued 11/5/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/17/2021 TSE MING HUANG
Applicant returned to address corrections 4/6/2021 STARR CHEN
Applicant returned to address corrections 5/1/2021 TSE MING HUANG
Plan Check Approved 5/12/2021 TSE MING HUANG
Issued 5/12/2021 APPLICANT
Building Plans Picked Up 5/25/2021 APPLICANT
CofO in Progress 6/11/2025 DAVID FEILER
Permit Finaled 6/11/2025 RICHARD STEINBACH
CofO Issued 6/11/2025 RICHARD STEINBACH
Permit Finaled 6/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/15/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 1/15/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/2/2021 DINAH GARIN
Sewer availability Cleared 2/2/2021 DINAH GARIN
Construction near power lines Cleared 3/18/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 5/12/2021 FARSHAD ALIMOHAMADI

Contact Information

Contractor Cavalier Builders Inc; Lic. No.: 758563-B 6520 PLATT AVE #732      WEST HILLS, CA 91307
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/1/2021 Not Ready for Inspection ENRIQUE MIRELES
Sewer 6/1/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/3/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/20/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 7/20/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 7/20/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 7/22/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/22/2021 Approved ENRIQUE MIRELES
Green Building Rough 7/22/2021 Approved ENRIQUE MIRELES
Insulation 7/23/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/26/2021 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Approved ENRIQUE MIRELES
Drywall Nailing 8/5/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/5/2021 Approved ENRIQUE MIRELES
Gas Test 8/24/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Gas Test 8/26/2021 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 10/6/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 10/6/2021 Approved ENRIQUE MIRELES
HVAC-Final 10/6/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 10/6/2021 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/6/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/12/2021 Approved ENRIQUE MIRELES
Final 10/12/2021 Corrections Issued ENRIQUE MIRELES
HVAC-Final 10/12/2021 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 10/12/2021 Approved ENRIQUE MIRELES
Final 6/11/2025 OK to Issue CofO DAVID FEILER