1488 W 19TH ST 90732
Certificate Information: 1488 W 19TH ST 90732
- Application / Permit
- 20014-10000-04570
- Plan Check / Job No.
- B20LA19315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 450 SF ADDITION TO (E) SFD TO ADD MBDR W/ MBA & WALK-IN CLOSET
- Permit Issued
- Issued on 1/28/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2020 | RAHEL BEYENE |
| Corrections Issued | 11/6/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 11/19/2020 | ADAM HEGAZI |
| Plan Check Approved | 11/30/2020 | ADAM HEGAZI |
| Issued | 1/28/2021 | APPLICANT |
| Building Plans Picked Up | 1/29/2021 | APPLICANT |
| CofO in Progress | 8/15/2022 | ANSON MAGLASANG |
| Permit Finaled | 8/16/2022 | DEROLD HAUFF |
| CofO Issued | 8/16/2022 | DEROLD HAUFF |
| Permit Finaled | 8/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/10/2020 | YEGANEH SADEGHI |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2020 | YEGANEH SADEGHI |
| Sewer availability | Cleared | 11/12/2020 | YEGANEH SADEGHI |
| Grading Pre-Inspection | Cleared | 11/19/2020 | RAHEL BEYENE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/1/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 2/1/2021 | Partial Inspection | JOHN KLARIN |
| Deputy Drilled-In Anchors | 2/3/2021 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/22/2021 | Approved | JOHN KLARIN |
| Wood Frame | 3/22/2021 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 4/6/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 4/6/2021 | Approved | JOHN KLARIN |
| Insulation | 4/16/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 4/23/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 4/23/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 4/28/2021 | Approved | JOHN KLARIN |
| Shower Pan | 6/21/2021 | Approved | ALFREDO BALANDRA |
| BUILDING-Rough-Frame | 3/17/2022 | Approved | ANSON MAGLASANG |
| Final | 3/17/2022 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/17/2022 | Approved | ANSON MAGLASANG |
| Green Building Final | 3/17/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 3/17/2022 | Corrections Issued | ANSON MAGLASANG |
| Final | 8/15/2022 | OK to Issue CofO | ANSON MAGLASANG |
| Smoke Detectors | 8/15/2022 | Approved | ANSON MAGLASANG |