1488 W 19TH ST 90732

Certificate Information: 1488 W 19TH ST 90732

Application / Permit
20014-10000-04570
Plan Check / Job No.
B20LA19315
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
450 SF ADDITION TO (E) SFD TO ADD MBDR W/ MBA & WALK-IN CLOSET
Permit Issued
Issued on 1/28/2021
Issuing Office
Current Status
CofO Issued on 8/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/30/2020 RAHEL BEYENE
Corrections Issued 11/6/2020 RAHEL BEYENE
Applicant returned to address corrections 11/19/2020 ADAM HEGAZI
Plan Check Approved 11/30/2020 ADAM HEGAZI
Issued 1/28/2021 APPLICANT
Building Plans Picked Up 1/29/2021 APPLICANT
CofO in Progress 8/15/2022 ANSON MAGLASANG
Permit Finaled 8/16/2022 DEROLD HAUFF
CofO Issued 8/16/2022 DEROLD HAUFF
Permit Finaled 8/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/10/2020 YEGANEH SADEGHI
Eng Process Fee Ord 176,300 Cleared 11/12/2020 YEGANEH SADEGHI
Sewer availability Cleared 11/12/2020 YEGANEH SADEGHI
Grading Pre-Inspection Cleared 11/19/2020 RAHEL BEYENE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/1/2021 Corrections Issued JOHN KLARIN
PLUMBING-Rough 2/1/2021 Partial Inspection JOHN KLARIN
Deputy Drilled-In Anchors 2/3/2021 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 2/9/2021 Approved JOHN KLARIN
PLUMBING-Rough 3/22/2021 Approved JOHN KLARIN
Wood Frame 3/22/2021 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 4/6/2021 Approved JOHN KLARIN
HVAC-Rough 4/6/2021 Approved JOHN KLARIN
Insulation 4/16/2021 Approved JOHN KLARIN
Drywall Nailing 4/23/2021 Approved JOHN KLARIN
Green Building Rough 4/23/2021 Approved JOHN KLARIN
Green Building Rough 4/28/2021 Approved JOHN KLARIN
Shower Pan 6/21/2021 Approved ALFREDO BALANDRA
BUILDING-Rough-Frame 3/17/2022 Approved ANSON MAGLASANG
Final 3/17/2022 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 3/17/2022 Approved ANSON MAGLASANG
Green Building Final 3/17/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 3/17/2022 Corrections Issued ANSON MAGLASANG
Final 8/15/2022 OK to Issue CofO ANSON MAGLASANG
Smoke Detectors 8/15/2022 Approved ANSON MAGLASANG