1824 W 65TH ST 90047
Certificate Information: 1824 W 65TH ST 90047
- Application / Permit
- 20014-10000-04534
- Plan Check / Job No.
- B20LA19186
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO DETACHED STORAGE TO CONVERT TO ADU AND ATTACH STRUCTURE TO EXISTING DETACHED GARAGE.
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2020 | RAHEL BEYENE |
| Corrections Issued | 11/6/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 2/1/2021 | CRISTINA SALAZAR |
| Plan Check Approved | 5/26/2021 | RICARDO RAMIREZ |
| Issued | 7/15/2021 | APPLICANT |
| Building Plans Picked Up | 7/19/2021 | APPLICANT |
| CofO in Progress | 7/13/2022 | ENRIQUE MIRELES |
| No Progress | 2/6/2023 | SCOTT FINNILA |
| CofO in Progress | 2/16/2023 | DEROLD HAUFF |
| Permit Finaled | 2/16/2023 | DEROLD HAUFF |
| CofO Issued | 2/16/2023 | DEROLD HAUFF |
| Permit Finaled | 2/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/19/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 1/22/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 1/22/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 1/22/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/20/2021 | Corrections Issued | FREDDIE RIVERA |
| Piling/Pier/Caisson | 9/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| PLUMBING-Rough | 9/24/2021 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 9/24/2021 | Order to Comply Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 10/5/2021 | Approved | FREDDIE RIVERA |
| Reinforced Concrete Frame | 10/5/2021 | Approved | FREDDIE RIVERA |
| Deputy Wood Construction | 11/2/2021 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/3/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/14/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/14/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/22/2022 | Conditional Approval | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 2/22/2022 | Approved | FREDDIE RIVERA |
| Insulation | 2/28/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 3/3/2022 | Approved | SCOTT FINNILA |
| Green Building Rough | 3/3/2022 | Approved | SCOTT FINNILA |
| Service/Power Release | 5/13/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | ENRIQUE MIRELES |
| Final | 6/8/2022 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | ENRIQUE MIRELES |
| Final | 6/15/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/15/2022 | Approved | ENRIQUE MIRELES |
| Green Building Final | 6/15/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/15/2022 | Approved | ENRIQUE MIRELES |
| Final | 7/12/2022 | OK to Issue CofO | ENRIQUE MIRELES |