3512 W ATWATER AVE 90039

Certificate Information: 3512 W ATWATER AVE 90039

Application / Permit
20014-10000-04527
Plan Check / Job No.
B20LA19133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY IRREG ADDITION WITH TRELLIS PATIO TO REAR OF (E) SFD. ADD SUNROOM AND OFFICE. ENLARGE MASTER BATHROOM.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/23/2020 LAWRENCE QUIRANTE
Corrections Issued 10/24/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/26/2021 CRISTINA SALAZAR
Plan Check Approved 4/8/2021 JESSE JIMENEZ
Issued 4/22/2021 APPLICANT
Building Plans Picked Up 5/11/2021 APPLICANT
CofO in Progress 11/19/2025 NICHOLAS LOPEZ
Permit Finaled 11/21/2025 DEROLD HAUFF
CofO Issued 11/21/2025 DEROLD HAUFF
Permit Finaled 11/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 1/19/2021 TERRI OSBORNE
Low Impact Development Cleared 1/27/2021 ORVAL HERNANDEZ-MARCI
Sewer availability Cleared 2/11/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/16/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 2/16/2021 JEANIE LAM

Contact Information

Contractor Watchful Eye Project Management; Lic. No.: 1039729-B 33125 N 81ST STREET      SCOTTSDALE, AZ 85266
Engineer Belmont,, Robert Paul; Lic. No.: C76732 599 HALKIRK ST      SANTA BARBARA, CA 93110

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/30/2021 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/30/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 7/29/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/3/2021 Partial Approval CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 Partial Approval CHARLES BOGHOSKHAN
Green Building Rough 8/3/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
Insulation 8/3/2021 Partial Approval CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 8/24/2021 Conditional Approval CHARLES BOGHOSKHAN
PLUMBING-Rough 9/8/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/23/2021 Approved HAMIK HARTOUNIAN
Shower Pan 9/23/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/26/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 10/26/2021 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/26/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/9/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 12/9/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 12/9/2021 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/10/2022 No Access for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/20/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/20/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 1/20/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/20/2022 Approved HAMIK HARTOUNIAN
Final 4/7/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 4/7/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 4/7/2022 Approved HAMIK HARTOUNIAN
Final 11/19/2025 OK to Issue CofO NICHOLAS LOPEZ