2676 N GLENDALE BLVD 1-4 90039
Certificate Information: 2676 N GLENDALE BLVD 1-4 90039
- Application / Permit
- 20014-10000-04512
- Plan Check / Job No.
- B20LA19063
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED ATTACHED TWO STORY ADU TO (E) 2 STORY DUPLEX BUILDING NEW KITCHEN, LIVING AND DINING AREA WITH 2 BEDROOMS AND 2 BATHROOMS (ATTACHED ADU PER ORDINANCE, 12.22 A 33 (c) AND (e))
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Corrected on 5/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | AUNG SOE |
| Corrections Issued | 12/2/2020 | AUNG SOE |
| Quality Review Completed | 12/14/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/10/2021 | AUNG SOE |
| Plan Check Approved | 5/10/2021 | AUNG SOE |
| Issued | 5/25/2021 | APPLICANT |
| Building Plans Picked Up | 5/27/2021 | APPLICANT |
| CofO in Progress | 3/2/2022 | THOMAS LOGRASSO |
| CofO Issued-Status Void | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled-Status Void | 3/5/2022 | DEROLD HAUFF |
| Re-Activate Permit | 5/18/2023 | DEROLD HAUFF |
| Permit Finaled | 5/23/2023 | DEROLD HAUFF |
| CofO Corrected | 5/23/2023 | DEROLD HAUFF |
| Permit Finaled | 5/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2021 | ROSA SILVA |
| Address approval | Cleared | 1/13/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/17/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 3/9/2021 | OSCAR CASTRO |
| Sewer availability | Cleared | 3/16/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 4/8/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | ROSA SILVA |
| Grading Pre-Inspection | Cleared | 5/8/2021 | AUNG SOE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/21/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/24/2021 | Conditional Approval | RUBEN SALAS |
| Wood Frame | 7/9/2021 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2021 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/3/2021 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 8/3/2021 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/3/2021 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/9/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/9/2021 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/2/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 9/2/2021 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 9/2/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 9/7/2021 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/13/2021 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 9/13/2021 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/13/2021 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/13/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 9/17/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/17/2021 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 9/27/2021 | Approved | THOMAS LOGRASSO |
| Shower Pan | 10/14/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/18/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/21/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 1/28/2022 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/28/2022 | No Access for Inspection | RAUL BARAJAS |
| Green Building Final | 1/28/2022 | Approved | RAUL BARAJAS |
| MERV13>=Final | 1/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| MERV13>=Rough | 1/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 1/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 2/24/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 2/24/2022 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Final | 2/24/2022 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 2/24/2022 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 2/24/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 2/24/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 3/1/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/1/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 3/1/2022 | Approved | THOMAS LOGRASSO |