1490 W 36TH ST 90018
Certificate Information: 1490 W 36TH ST 90018
- Application / Permit
- 20014-10000-04503
- Plan Check / Job No.
- B20LA19038
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION FROM GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)&(d). All work per Engineer Design.
- Permit Issued
- Issued on 7/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | ZAW HAN |
| Corrections Issued | 11/16/2020 | ZAW HAN |
| Quality Review Completed | 11/25/2020 | TU HUA |
| Building Plans Picked Up | 12/1/2020 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | ZAW HAN |
| Plan Check Approved | 6/23/2022 | ZAW HAN |
| Issued | 7/1/2022 | APPLICANT |
| CofO in Progress | 12/22/2022 | SABAS ALONSO |
| Permit Finaled | 2/4/2023 | DEROLD HAUFF |
| CofO Issued | 2/4/2023 | DEROLD HAUFF |
| Permit Finaled | 2/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/24/2021 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 4/27/2021 | MICHAEL SOTO |
| Abandoned oil well | Cleared | 9/6/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/4/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | THAN WIN |
| Green Code | Cleared | 4/21/2022 | ZAW HAN |
| Address approval | Cleared | 5/23/2022 | CINDY QI |
Contact Information
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
| Engineer | Cheek,, Gary Albert; Lic. No.: C36253 | PO BOX 216 MAYWOOD, CA 90270 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2022 | No Access for Inspection | SABAS ALONSO |
| METHANE-Barrier | 7/19/2022 | No Access for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 7/19/2022 | No Access for Inspection | SABAS ALONSO |
| Underground Mechanical | 7/19/2022 | No Access for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/22/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 7/26/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 7/26/2022 | Approved | SABAS ALONSO |
| METHANE-Barrier | 7/26/2022 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 7/26/2022 | Approved | SABAS ALONSO |
| Sewer | 7/26/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/26/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 8/26/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/26/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 8/26/2022 | Approved | STUART CHAPMAN |
| METHANE-Rough | 8/26/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 8/26/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 8/26/2022 | Corrections Issued | STUART CHAPMAN |
| Insulation | 8/31/2022 | Corrections Issued | SABAS ALONSO |
| Insulation | 9/7/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 9/14/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/14/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/14/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 9/19/2022 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 9/23/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 12/7/2022 | Approved | SABAS ALONSO |
| Final | 12/7/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/7/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 12/7/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 12/7/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 12/7/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 12/12/2022 | Approved | SABAS ALONSO |
| Final | 12/12/2022 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 12/12/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 12/12/2022 | Approved | SABAS ALONSO |
| Final | 12/21/2022 | OK to Issue CofO | SABAS ALONSO |