5935 W 77TH PL 90045
Certificate Information: 5935 W 77TH PL 90045
- Application / Permit
- 20014-10000-04475
- Plan Check / Job No.
- B20LA18939
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO (E) SINGLE FAMILY DWELLING. CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 5/28/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/26/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 12/15/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 4/8/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/5/2021 | DANIEL YIP |
| Issued | 5/28/2021 | APPLICANT |
| Building Plans Picked Up | 6/3/2021 | APPLICANT |
| CofO in Progress | 2/13/2023 | BOBBY KEY |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
| CofO Issued | 2/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/26/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 4/30/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2021 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 6/29/2021 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/13/2021 | Conditional Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/9/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 12/20/2021 | Approved | BOBBY KEY |
| HVAC-Rough | 12/20/2021 | Approved | BOBBY KEY |
| Insulation | 12/20/2021 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/20/2021 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 12/21/2021 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/21/2021 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/21/2021 | Approved | BOBBY KEY |
| Drywall Nailing | 2/10/2022 | Approved | CLAYTON GRAHAM |
| Shower Pan | 6/27/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/27/2022 | Partial Inspection | HERBERT GIRON |
| Final | 1/31/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 1/31/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 1/31/2023 | Corrections Issued | BOBBY KEY |
| Final | 2/13/2023 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 2/13/2023 | Approved | BOBBY KEY |