1120 S GRAND AVE 101 90015
Certificate Information: 1120 S GRAND AVE 101 90015
- Application / Permit
- 20014-10000-04468
- Plan Check / Job No.
- B20LA18901
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- ADDITION OF A 38'-4" X 18,-0" EXTERIOR STEEL TRELLIS , INTERIOR IMPROVEMENTS, AND MODIFICATION OF EXISTING STOREFRONT.
- Permit Issued
- Issued on 6/1/2021
- Issuing Office
- Current Status
- CofO Issued on 5/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | JOHNNY WU |
| Disabled Access Plans Picked Up | 11/30/2020 | APPLICANT |
| Corrections Issued | 12/1/2020 | JOHNNY WU |
| Quality Review Completed | 12/8/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 3/1/2021 | JOHNNY WU |
| Applicant returned to address corrections | 3/12/2021 | JOHNNY WU |
| Applicant returned to address corrections | 4/21/2021 | JOHNNY WU |
| Applicant returned to address corrections | 4/23/2021 | JOHNNY WU |
| Plan Check Approved | 5/11/2021 | JOHNNY WU |
| Issued | 6/1/2021 | APPLICANT |
| Building Plans Picked Up | 6/2/2021 | APPLICANT |
| CofO in Progress | 5/16/2022 | TED RIES |
| Permit Finaled | 5/16/2022 | TED RIES |
| CofO Issued | 5/16/2022 | TED RIES |
| Permit Finaled | 5/16/2022 | TED RIES |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/14/2020 | SHINE LIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 2/24/2021 | CECILIO NAVARRO |
| "D" conditions | Cleared | 3/2/2021 | JOE LUCKEY |
| "Q" conditions | Cleared | 3/2/2021 | JOE LUCKEY |
| Tract Map conditions | Cleared | 3/2/2021 | JOE LUCKEY |
| Tract Map conditions | Cleared | 3/2/2021 | JOE LUCKEY |
| ZA Case | Cleared | 3/2/2021 | JOE LUCKEY |
| Historic Resource Verification | Cleared | 3/11/2021 | MICAELA TORRES-GIL |
| Highway dedication | Cleared | 3/17/2021 | RENZ SORIANO |
| Redevelopment Project Area | Cleared | 3/23/2021 | GRACIELA ACOSTA |
| Green Code | Cleared | 3/25/2021 | MICHAEL AYERS |
Contact Information
| Contractor | Red Tech Service Commercial Refrigeration; Lic. No.: 928471-B | 12714 BASSETT STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| T-Bar Ceiling | 10/14/2021 | Conditional Approval | JONATHAN QUACH |
| Final | 12/3/2021 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 12/3/2021 | Approved | TIMOTHY BUXTON |
| Green Building Final | 12/3/2021 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 12/3/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Barrier | 12/3/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 12/3/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 12/3/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 12/3/2021 | Approved | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 12/3/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 12/3/2021 | Approved | TIMOTHY BUXTON |
| Special/Order Compliance | 1/25/2022 | Corrections Issued | TED RIES |
| Special/Order Compliance | 1/31/2022 | Corrections Issued | TED RIES |
| Special/Order Compliance | 2/10/2022 | Approved | TED RIES |
| Special/Order Compliance | 2/10/2022 | Partial Approval | TIMOTHY BUXTON |