7707 N ELMER AVE 91352

Certificate Information: 7707 N ELMER AVE 91352

Application / Permit
20014-10000-04443
Plan Check / Job No.
B20LA18780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. PROPOSED 1-STORY ADDITION TO SINGLE FAMILY DWELLING AT REAR
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 MONICA RAMIREZ
Corrections Issued 10/19/2020 MONICA RAMIREZ
Quality Review Completed 11/5/2020 TU HUA
Applicant returned to address corrections 9/23/2021 MONICA RAMIREZ
Plan Check Approved 10/5/2021 MONICA RAMIREZ
Issued 10/7/2021 APPLICANT
CofO in Progress 12/7/2022 MATTHEW NELSON
Permit Finaled 12/24/2022 MICHAEL SMITH
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/14/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/14/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/25/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/14/2022 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 4/14/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 6/8/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/7/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/7/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 7/7/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 7/7/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/7/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 7/15/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 7/19/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 8/1/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/1/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/6/2022 Approved CHRISTOPHER DELLEFIELD
Final 10/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 10/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 10/6/2022 Approved CHRISTOPHER DELLEFIELD
Final 11/15/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Final 11/15/2022 Approved CHRISTOPHER DELLEFIELD
Final 12/6/2022 OK to Issue CofO MATTHEW NELSON
HVAC-Final 12/6/2022 Approved MATTHEW NELSON
PLUMBING-Final 12/6/2022 Approved MATTHEW NELSON