418 N MESA ST 90731
Certificate Information: 418 N MESA ST 90731
- Application / Permit
- 20014-10000-04433
- Plan Check / Job No.
- B20LA18731
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 8/26/2021
- Issuing Office
- Current Status
- CofO Issued on 1/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | DANIEL YIP |
| Corrections Issued | 11/6/2020 | DANIEL YIP |
| Quality Review Completed | 11/12/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Applicant returned to address corrections | 2/3/2021 | DANIEL YIP |
| Applicant returned to address corrections | 6/22/2021 | DANIEL YIP |
| Plan Check Approved | 8/17/2021 | DANIEL YIP |
| Issued | 8/26/2021 | APPLICANT |
| CofO in Progress | 1/19/2024 | JAMES CHAVEZ |
| Permit Finaled | 1/19/2024 | ANSON MAGLASANG |
| CofO Issued | 1/19/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/19/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2021 | CHINH DINH |
| Community Plan Implem. Overlay | Cleared | 2/9/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | CHINH DINH |
| Sewer availability | Cleared | 2/22/2021 | CHINH DINH |
| Historic Resource Verification | Cleared | 2/23/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 3/8/2021 | DAVID URITA |
| Hydrant and Access approval | Cleared | 4/9/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 5/16/2021 | MARTIN FRAGOSO |
| Community Plan Implem. Overlay | Cleared | 6/23/2021 | JEANALEE OBERGFELL |
| Grading Pre-Inspection | Cleared | 7/21/2021 | BRIAN MILLER |
| GPI Written Notices | Cleared | 8/13/2021 | DANIEL YIP |
Contact Information
| Contractor | Affordable Building Solutions Inc; Lic. No.: 1068574-B | 8885 SANDALWOOD CT RANCHO CUCAMONGA, CA 91730 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/30/2021 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/10/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Pre-Inspection | 9/10/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Underground Mechanical | 9/10/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 9/13/2021 | Corrections Issued | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 9/28/2021 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 11/1/2021 | No Access for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 11/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 11/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 11/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 11/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 11/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/24/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 11/24/2021 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 11/24/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 11/24/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/11/2022 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 3/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 3/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 3/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 3/11/2022 | Approved | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 3/11/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 4/28/2022 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/28/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/28/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/28/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/28/2022 | Partial Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 4/28/2022 | Approved | EUGENE CASSIDY |
| Insulation | 5/27/2022 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 5/27/2022 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 6/13/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 6/15/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 6/15/2022 | Conditional Approval | ANSON MAGLASANG |
| Drywall Nailing | 6/23/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/23/2022 | Partial Approval | JOHN KLARIN |
| Pre-Inspection | 3/14/2023 | Partial Inspection | ANSON MAGLASANG |
| Special/Order Compliance | 3/14/2023 | Partial Inspection | ANSON MAGLASANG |
| ELECTRICAL-Final | 5/25/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 5/25/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 5/25/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 6/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 6/21/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 6/21/2023 | Approved | JOHN KLARIN |
| Gas Test | 6/21/2023 | Approved | JOHN KLARIN |
| Green Building Final | 6/21/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 6/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Final | 6/21/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 6/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 6/21/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 8/10/2023 | Approved | JOHN KLARIN |
| Final | 8/10/2023 | Corrections Issued | JOHN KLARIN |
| Gas Test | 8/10/2023 | Approved | JOHN KLARIN |
| Green Building Final | 8/10/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 8/10/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Final | 8/10/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 8/10/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 9/18/2023 | Corrections Issued | JAMES CHAVEZ |
| Service/Power Release | 9/18/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 11/7/2023 | Corrections Issued | JAMES CHAVEZ |
| Gas Test | 11/7/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Service/Power Release | 11/7/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 1/16/2024 | OK to Issue CofO | JAMES CHAVEZ |
| Service/Power Release | 1/16/2024 | Approved | JAMES CHAVEZ |