2032 S OVERLAND AVE 90025

Certificate Information: 2032 S OVERLAND AVE 90025

Application / Permit
20014-10000-04427
Plan Check / Job No.
B20LA18706
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERT EXISTING RECREATIONAL ROOM TO NEW ADU WITH NO ADDITIONAL FLOOR AREA PER STATE LAW
Permit Issued
Issued on 12/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 DANIEL YIP
Corrections Issued 10/19/2020 DANIEL YIP
Plan Check Approved 12/2/2020 AMIR DANAI
Building Plans Picked Up 12/3/2020 APPLICANT
Issued 12/22/2020 APPLICANT
CofO in Progress 3/22/2023 STEPHANIE SWANSON
Permit Finaled 3/22/2023 DANIEL ORRANTE
CofO Issued 3/22/2023 DANIEL ORRANTE
Permit Finaled 3/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/18/2020 SAUL GARCIA
Sewer availability Cleared 11/18/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 11/20/2020 SAUL GARCIA

Contact Information

Contractor A B C Aguero'S Builders Company Inc; Lic. No.: 808359-B 3040 ROSWELL STREET      LOS ANGELES, CA 90065

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 12/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 12/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 1/12/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/12/2021 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 1/12/2021 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 1/19/2021 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Rough 1/19/2021 Corrections Issued ANTHONY MCDOWALL
Sewer 1/19/2021 Corrections Issued ANTHONY MCDOWALL
ELECTRICAL-Rough 1/27/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/27/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/27/2021 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 1/27/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 2/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/17/2021 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 2/17/2021 Approved GERMAN RODRIGUEZ MENDOZA
Sewer 2/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sewer 2/23/2021 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 3/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 4/15/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 4/15/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 4/26/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Final 4/26/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Final 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 4/26/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 4/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 5/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 5/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 5/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Final 5/12/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA