14957 W SEPTO ST 91345

Certificate Information: 14957 W SEPTO ST 91345

Application / Permit
20014-10000-04423
Plan Check / Job No.
B20LA18674
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: 20' X 16' ADDITION TO EXISTING SFD per WFPP.
Permit Issued
Issued on 1/29/2021
Issuing Office
Current Status
CofO Issued on 9/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 11/4/2020 CRYSTEL MAALOUF
Corrections Issued 11/12/2020 CRYSTEL MAALOUF
Quality Review Completed 11/20/2020 MINYE PAK
Applicant returned to address corrections 12/22/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 1/11/2021 CRYSTEL MAALOUF
Plan Check Approved 1/25/2021 CRYSTEL MAALOUF
Issued 1/29/2021 APPLICANT
CofO in Progress 7/14/2021 JENNIFER RABUCHIN
Permit Finaled 9/2/2021 MICHAEL SMITH
CofO Issued 9/2/2021 MICHAEL SMITH
Permit Finaled 9/2/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/19/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 11/19/2020 ADRIAN CASTRO
Sewer availability Cleared 11/19/2020 ADRIAN CASTRO

Contact Information

Contractor D H Property Maintenance Inc; Lic. No.: 985811-B       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/16/2021 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 2/16/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 3/17/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/24/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 4/6/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/6/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/21/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/21/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 4/21/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/21/2021 Approved JENNIFER RABUCHIN
Insulation 4/29/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/29/2021 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 5/19/2021 No Access for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 5/19/2021 No Access for Inspection KRISTEN CAUSEY
Drywall Nailing 5/21/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 5/21/2021 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 7/8/2021 Approved JENNIFER RABUCHIN
Final 7/8/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/8/2021 Approved JENNIFER RABUCHIN
Green Building Rough 7/8/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/8/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/8/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/13/2021 Approved JENNIFER RABUCHIN
Final 7/13/2021 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 7/13/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/13/2021 Approved JENNIFER RABUCHIN