3950 S ROXTON AVE 90008
Certificate Information: 3950 S ROXTON AVE 90008
- Application / Permit
- 20014-10000-04417
- Plan Check / Job No.
- B20LA18636
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) ONE STORY SFD
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2020 | FERNANDO FLORES |
| Corrections Issued | 10/21/2020 | FERNANDO FLORES |
| Building Plans Picked Up | 10/26/2020 | APPLICANT |
| Plan Check Approved | 4/8/2021 | LARRY LEE |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 7/11/2023 | ANTHONY EGSON |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
| CofO Issued | 7/18/2023 | DEROLD HAUFF |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/11/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2020 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 4/16/2021 | Off-Hour Fees Due | |
| Pre-Inspection | 4/16/2021 | Off-Hour Fees Due | |
| Deputy Drilled-In Anchors | 4/27/2021 | Conditional Approval | DAVID FEILER |
| Deputy Drilled-In Anchors | 4/28/2021 | No Access for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 4/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Pre-Inspection | 4/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/6/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/6/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 5/6/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Corrections Issued | DAVID FEILER |
| Insulation | 7/13/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 7/14/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 7/14/2021 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 7/20/2021 | No Access for Inspection | DAVID FEILER |
| Wood Frame | 8/25/2021 | Not Ready for Inspection | DAVID FEILER |
| Deputy Wood Construction | 9/1/2021 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Partial Approval | DAVID FEILER |
| Special/Order Compliance | 9/7/2021 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 9/9/2022 | Partial Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Corrections Issued | ANTHONY EGSON |
| Deputy Wood Construction | 9/26/2022 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 11/16/2022 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 12/6/2022 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 12/9/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 12/22/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/22/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/22/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/29/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/29/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/29/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/10/2023 | Approved | ANTHONY EGSON |
| Final | 4/28/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 4/28/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/28/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/14/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 6/14/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 6/14/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 6/14/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 6/14/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/26/2023 | Approved | ANTHONY EGSON |
| Final | 6/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 6/26/2023 | Approved | ANTHONY EGSON |
| Final | 7/11/2023 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 7/11/2023 | Approved | ANTHONY EGSON |