549 W AVENUE 26 90065
Certificate Information: 549 W AVENUE 26 90065
- Application / Permit
- 20014-10000-04381
- Plan Check / Job No.
- B20LA18522
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition (290 sq ft) to existing barber shop (213 sq ft)structure and convert to ADU.
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Current Status
- CofO Issued on 9/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | JOE VO |
| Corrections Issued | 11/18/2020 | JOE VO |
| Quality Review Completed | 12/18/2020 | MINYE PAK |
| Plan Check Approved | 2/16/2021 | JOE VO |
| Issued | 2/18/2021 | APPLICANT |
| CofO in Progress | 8/16/2022 | OSVALDO PARAMO |
| CofO in Progress | 8/16/2022 | OSVALDO PARAMO |
| Permit Finaled | 9/6/2022 | DEROLD HAUFF |
| CofO Issued | 9/6/2022 | DEROLD HAUFF |
| Permit Finaled | 9/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/26/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/27/2021 | CECILIO NAVARRO |
| CPC | Cleared | 1/28/2021 | SARAHI ORTEGA |
| ZI | Cleared | 1/28/2021 | SARAHI ORTEGA |
| Address approval | Cleared | 1/29/2021 | CECILIO NAVARRO |
| Certificate of Compliance | Cleared | 2/2/2021 | MARC WOERSCHING |
| Supp. Use District POD/CDO/TDO | Cleared | 2/9/2021 | ADRINEH MELKONIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2021 | Conditional Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 5/18/2021 | Approved | LANNY MERRICK |
| Wood Frame | 9/28/2021 | Not Ready for Inspection | MARK FERRARI |
| BUILDING-Rough-Frame | 10/4/2021 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 10/4/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/8/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/26/2021 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 10/26/2021 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 10/26/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 10/26/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/1/2021 | Approved | OSVALDO PARAMO |
| Insulation | 11/1/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/1/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 11/8/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/18/2022 | Corrections Issued | OSVALDO PARAMO |
| Final | 3/23/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/23/2022 | Approved | OSVALDO PARAMO |
| MERV13>=Final | 3/23/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 3/23/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 3/29/2022 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 3/29/2022 | Approved | OSVALDO PARAMO |