5850 W 77TH PL 90045
Certificate Information: 5850 W 77TH PL 90045
- Application / Permit
- 20014-10000-04375
- Plan Check / Job No.
- B20LA18483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1ST FLOOR GARAGE ADDITION AND REMODEL 2ND FLOOR ADDITION TO NEW ADU
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- Issued on 4/26/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 11/10/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/18/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Applicant returned to address corrections | 1/6/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 2/18/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/23/2021 | MAHNAZ NOURHASHEMI |
| Issued | 4/26/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2020 | SAUL GARCIA |
| Sewer availability | Cleared | 12/16/2020 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 1/7/2021 | BARTON HOLMES |
| Hydrant and Access approval | Cleared | 2/23/2021 | MATTHEW CRAIG |
| Specific Plan | Cleared | 3/2/2021 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 3/8/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/12/2021 | DINAH GARIN |
Contact Information
| Contractor | Ludis Inc; Lic. No.: 1061815-B | 3415 S SEPULVEDA BLVD STE 1100 LOS ANGELES, CA 90034 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/17/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 5/17/2021 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/21/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 5/21/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 6/30/2021 | Partial Inspection | AMY COLIN |
| Footing/Foundation/Slab | 7/9/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 7/16/2021 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2021 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 11/18/2021 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2022 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 2/24/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/11/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/11/2022 | Corrections Issued | BOBBY KEY |
| Wood Frame | 4/11/2022 | Not Ready for Inspection | BOBBY KEY |
| Deputy Wood Construction | 4/12/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 8/10/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 8/10/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 8/10/2022 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 8/30/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 8/30/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/30/2022 | Approved | BOBBY KEY |
| Service/Power Release | 8/30/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/5/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 10/5/2022 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 10/5/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 12/8/2022 | Not Ready for Inspection | HERBERT GIRON |
| Service/Power Release | 12/8/2022 | Approved | HERBERT GIRON |
| Service/Power Release | 12/9/2022 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 3/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 3/16/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/28/2023 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 3/28/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/17/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 4/17/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 4/17/2023 | Approved | BOBBY KEY |
| Insulation | 4/17/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/1/2023 | Approved | BOBBY KEY |
| Shower Pan | 5/1/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/25/2023 | Corrections Issued | BOBBY KEY |
| Final | 8/25/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 8/25/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 8/25/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 8/25/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 10/18/2023 | Corrections Issued | BOBBY KEY |
| Final | 10/18/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 10/18/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 10/18/2023 | Conditional Approval | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 10/18/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/16/2026 | Partial Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 1/21/2026 | Approved | JESUS PINEDA |
| Final | 1/21/2026 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 1/21/2026 | Partial Approval | JESUS PINEDA |
| PLUMBING-Final | 1/21/2026 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | JESUS PINEDA |