5850 W 77TH PL 90045

Certificate Information: 5850 W 77TH PL 90045

Application / Permit
20014-10000-04375
Plan Check / Job No.
B20LA18483
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1ST FLOOR GARAGE ADDITION AND REMODEL 2ND FLOOR ADDITION TO NEW ADU
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
Issued on 4/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 MAHNAZ NOURHASHEMI
Corrections Issued 11/10/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 11/18/2020 TIEN JEN WANG
Building Plans Picked Up 11/19/2020 APPLICANT
Applicant returned to address corrections 1/6/2021 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 2/18/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 4/23/2021 MAHNAZ NOURHASHEMI
Issued 4/26/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/16/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 12/16/2020 SAUL GARCIA
Sewer availability Cleared 12/16/2020 SAUL GARCIA
Grading Pre-Inspection Cleared 1/7/2021 BARTON HOLMES
Hydrant and Access approval Cleared 2/23/2021 MATTHEW CRAIG
Specific Plan Cleared 3/2/2021 EDUARDO HERMOSO
Low Impact Development Cleared 3/8/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/12/2021 DINAH GARIN

Contact Information

Contractor Ludis Inc; Lic. No.: 1061815-B 3415 S SEPULVEDA BLVD STE 1100      LOS ANGELES, CA 90034
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 5/17/2021 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 5/17/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 5/21/2021 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 5/21/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 6/30/2021 Partial Inspection AMY COLIN
Footing/Foundation/Slab 7/9/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 7/16/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/17/2021 Corrections Issued BOBBY KEY
Special/Order Compliance 11/18/2021 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Conditional Approval BOBBY KEY
Special/Order Compliance 2/24/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 4/11/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 4/11/2022 Corrections Issued BOBBY KEY
Wood Frame 4/11/2022 Not Ready for Inspection BOBBY KEY
Deputy Wood Construction 4/12/2022 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 8/10/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Corrections Issued BOBBY KEY
HVAC-Rough 8/10/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 8/10/2022 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 8/30/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 8/30/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Approved BOBBY KEY
PLUMBING-Rough 8/30/2022 Approved BOBBY KEY
Service/Power Release 8/30/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 10/5/2022 Not Ready for Inspection BOBBY KEY
HVAC-Rough 10/5/2022 Not Ready for Inspection BOBBY KEY
Insulation 10/5/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 12/8/2022 Not Ready for Inspection HERBERT GIRON
Service/Power Release 12/8/2022 Approved HERBERT GIRON
Service/Power Release 12/9/2022 Approved RICHARD STEINBACH
Interior/Exterior Lathing 3/1/2023 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 3/16/2023 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 3/28/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 3/28/2023 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 4/17/2023 Approved BOBBY KEY
Drywall Nailing 4/17/2023 Approved BOBBY KEY
HVAC-Rough 4/17/2023 Approved BOBBY KEY
Insulation 4/17/2023 Approved BOBBY KEY
Interior/Exterior Lathing 5/1/2023 Approved BOBBY KEY
Shower Pan 5/1/2023 Approved BOBBY KEY
ELECTRICAL-Final 8/25/2023 Corrections Issued BOBBY KEY
Final 8/25/2023 Corrections Issued BOBBY KEY
HVAC-Final 8/25/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 8/25/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 8/25/2023 SGSOV Not Ready BOBBY KEY
Smoke Detectors 8/25/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 10/18/2023 Corrections Issued BOBBY KEY
Final 10/18/2023 Corrections Issued BOBBY KEY
HVAC-Final 10/18/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 10/18/2023 Conditional Approval BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Not Ready BOBBY KEY
Smoke Detectors 10/18/2023 Approved BOBBY KEY
ELECTRICAL-Final 1/16/2026 Partial Inspection WILBER ROSALES
ELECTRICAL-Final 1/21/2026 Approved JESUS PINEDA
Final 1/21/2026 Corrections Issued JESUS PINEDA
HVAC-Final 1/21/2026 Partial Approval JESUS PINEDA
PLUMBING-Final 1/21/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Approved JESUS PINEDA