4470 E BEAUVAIS AVE 90065

Certificate Information: 4470 E BEAUVAIS AVE 90065

Application / Permit
20014-10000-04368
Plan Check / Job No.
B20LA18420
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 9/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 DANIEL YIP
Corrections Issued 11/10/2020 DANIEL YIP
Quality Review Completed 11/19/2020 ALLEN MANALANSAN
Building Plans Picked Up 11/23/2020 APPLICANT
Plan Check Approved 2/26/2021 DANIEL YIP
Issued 3/1/2021 APPLICANT
CofO in Progress 9/25/2021 OSVALDO PARAMO
CofO in Progress 9/25/2021 OSVALDO PARAMO
Permit Finaled 9/29/2021 DEROLD HAUFF
CofO Issued 9/29/2021 DEROLD HAUFF
Permit Finaled 9/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 1/8/2021 DYLAN LAWRENCE
BHO/Hillside ordinance Cleared 1/26/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 1/26/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 1/26/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 1/26/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/27/2021 CELINA MORENO
Grading Pre-Inspection Cleared 2/5/2021 PATRICK MISCHLICH
GPI Written Notices Cleared 2/24/2021 ALLEN MANALANSAN

Contact Information

Contractor Jass Construction Services; Lic. No.: 982803-B 2684 LACY ST #202      LOS ANGELES, CA 90031
Engineer Kim,, Taewon; Lic. No.: C80632 2800 PLAZA DEL AMO UNIT 161      TORRANCE, CA 90503

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2021 Approved OSVALDO PARAMO
Wood Frame 3/19/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/20/2021 Partial Approval MISAEL ESPARZA
Insulation 3/20/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 4/1/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 4/7/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 4/7/2021 Approved HAMIK HARTOUNIAN
Insulation 4/7/2021 Order to Comply Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/7/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/9/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 4/9/2021 Approved HAMIK HARTOUNIAN
Insulation 4/9/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 7/26/2021 Approved BRAD BESCOS
Final 7/26/2021 Not Ready for Inspection BRAD BESCOS
Gas Test 7/26/2021 Corrections Issued BRAD BESCOS
Green Building Final 7/26/2021 Not Ready for Inspection BRAD BESCOS
Smoke Detectors 7/26/2021 Corrections Issued BRAD BESCOS
Final 7/28/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 7/28/2021 No Access for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/28/2021 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 7/28/2021 Corrections Issued HAMIK HARTOUNIAN
Final 8/5/2021 Corrections Issued OSVALDO PARAMO
Green Building Final 8/5/2021 Approved OSVALDO PARAMO
Smoke Detectors 8/5/2021 Approved OSVALDO PARAMO
Final 8/9/2021 OK to Issue CofO OSVALDO PARAMO