4470 E BEAUVAIS AVE 90065
Certificate Information: 4470 E BEAUVAIS AVE 90065
- Application / Permit
- 20014-10000-04368
- Plan Check / Job No.
- B20LA18420
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 3/1/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | DANIEL YIP |
| Corrections Issued | 11/10/2020 | DANIEL YIP |
| Quality Review Completed | 11/19/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Plan Check Approved | 2/26/2021 | DANIEL YIP |
| Issued | 3/1/2021 | APPLICANT |
| CofO in Progress | 9/25/2021 | OSVALDO PARAMO |
| CofO in Progress | 9/25/2021 | OSVALDO PARAMO |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/8/2021 | DYLAN LAWRENCE |
| BHO/Hillside ordinance | Cleared | 1/26/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/26/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/26/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/26/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 2/5/2021 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 2/24/2021 | ALLEN MANALANSAN |
Contact Information
| Contractor | Jass Construction Services; Lic. No.: 982803-B | 2684 LACY ST #202 LOS ANGELES, CA 90031 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 2800 PLAZA DEL AMO UNIT 161 TORRANCE, CA 90503 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 3/19/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2021 | Partial Approval | MISAEL ESPARZA |
| Insulation | 3/20/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/1/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 4/7/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/7/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/7/2021 | Order to Comply Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/7/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/9/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/9/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/9/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/26/2021 | Approved | BRAD BESCOS |
| Final | 7/26/2021 | Not Ready for Inspection | BRAD BESCOS |
| Gas Test | 7/26/2021 | Corrections Issued | BRAD BESCOS |
| Green Building Final | 7/26/2021 | Not Ready for Inspection | BRAD BESCOS |
| Smoke Detectors | 7/26/2021 | Corrections Issued | BRAD BESCOS |
| Final | 7/28/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 7/28/2021 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/28/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 8/5/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 8/5/2021 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 8/5/2021 | Approved | OSVALDO PARAMO |
| Final | 8/9/2021 | OK to Issue CofO | OSVALDO PARAMO |