3813 S ROXTON AVE 90008
Certificate Information: 3813 S ROXTON AVE 90008
- Application / Permit
- 20014-10000-04358
- Plan Check / Job No.
- B20LA18363
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION AND ADDITION FOR NEW ACCESSORY DWELLING UNIT. ALL WORK PER TYPE V SHEET. "COMPLY WITH DEPARTMENT ORDER effective date 02/16/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- CofO in Progress on 9/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/14/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 10/20/2020 | APPLICANT |
| Plan Check Approved | 12/14/2020 | FARSHAD ALIMOHAMADI |
| Issued | 7/6/2021 | APPLICANT |
| CofO in Progress | 9/9/2025 | WILLIAM MICHALAK |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 11/25/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | JEANIE LAM |
| Sewer availability | Cleared | 12/4/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/3/2021 | Partial Approval | GLEN RAND |
| Pre-Inspection | 8/13/2021 | Approved | GLEN RAND |
| Footing/Foundation/Slab | 8/20/2021 | Approved | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Approved | GLEN RAND |
| PLUMBING-Rough | 9/22/2021 | Corrections Issued | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 10/18/2021 | Corrections Issued | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 10/29/2021 | Approved | GLEN RAND |
| Wood Frame | 11/1/2021 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 11/5/2021 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | GLEN RAND |
| Green Building Rough | 11/9/2021 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 11/9/2021 | Approved | GLEN RAND |
| Insulation | 1/14/2022 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 1/25/2022 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 1/25/2022 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Final | 2/11/2022 | Partial Approval | WILLIAM MICHALAK |
| Sewer | 2/11/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Shower Pan | 2/11/2022 | Approved | WILLIAM MICHALAK |
| Gas Test | 2/18/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| HVAC-Rough | 2/18/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Sewer | 2/18/2022 | Corrections Issued | WILLIAM MICHALAK |
| Underground Mechanical | 2/18/2022 | Corrections Issued | WILLIAM MICHALAK |
| Gas Test | 2/24/2022 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Final | 4/5/2022 | Partial Approval | WILLIAM MICHALAK |
| Underground Mechanical | 4/7/2022 | Approved | WILLIAM MICHALAK |
| Final | 5/27/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 5/27/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 5/27/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 6/2/2022 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Final | 6/2/2022 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 6/2/2022 | Approved | WILLIAM MICHALAK |
| Final | 7/27/2022 | Corrections Issued | WILLIAM MICHALAK |
| Final | 8/5/2022 | Conditional Approval | WILLIAM MICHALAK |
| Final | 5/30/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Service/Power Release | 5/30/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 9/9/2025 | OK to Issue CofO | WILLIAM MICHALAK |