3813 S ROXTON AVE 90008

Certificate Information: 3813 S ROXTON AVE 90008

Application / Permit
20014-10000-04358
Plan Check / Job No.
B20LA18363
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION AND ADDITION FOR NEW ACCESSORY DWELLING UNIT. ALL WORK PER TYPE V SHEET. "COMPLY WITH DEPARTMENT ORDER effective date 02/16/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/6/2021
Issuing Office
Current Status
CofO in Progress on 9/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 10/13/2020 LAWRENCE QUIRANTE
Corrections Issued 10/14/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 10/20/2020 APPLICANT
Plan Check Approved 12/14/2020 FARSHAD ALIMOHAMADI
Issued 7/6/2021 APPLICANT
CofO in Progress 9/9/2025 WILLIAM MICHALAK

Permit Application Clearance Information

Address approval Cleared 11/25/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 11/25/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 12/2/2020 JEANIE LAM
Sewer availability Cleared 12/4/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/3/2021 Partial Approval GLEN RAND
Pre-Inspection 8/13/2021 Approved GLEN RAND
Footing/Foundation/Slab 8/20/2021 Approved GLEN RAND
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Approved GLEN RAND
PLUMBING-Rough 9/22/2021 Corrections Issued GLEN RAND
Rough-Elec/Plmb/HVAC 10/18/2021 Corrections Issued GLEN RAND
Rough-Elec/Plmb/HVAC 10/29/2021 Approved GLEN RAND
Wood Frame 11/1/2021 Approved GLEN RAND
Interior/Exterior Lathing 11/5/2021 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 11/9/2021 Approved GLEN RAND
Green Building Rough 11/9/2021 Approved GLEN RAND
Interior/Exterior Lathing 11/9/2021 Approved GLEN RAND
Insulation 1/14/2022 Approved WILLIAM MICHALAK
Drywall Nailing 1/25/2022 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 1/25/2022 Approved WILLIAM MICHALAK
ELECTRICAL-Final 2/11/2022 Partial Approval WILLIAM MICHALAK
Sewer 2/11/2022 Not Ready for Inspection WILLIAM MICHALAK
Shower Pan 2/11/2022 Approved WILLIAM MICHALAK
Gas Test 2/18/2022 Not Ready for Inspection WILLIAM MICHALAK
HVAC-Rough 2/18/2022 Not Ready for Inspection WILLIAM MICHALAK
Sewer 2/18/2022 Corrections Issued WILLIAM MICHALAK
Underground Mechanical 2/18/2022 Corrections Issued WILLIAM MICHALAK
Gas Test 2/24/2022 Corrections Issued WILLIAM MICHALAK
PLUMBING-Final 4/5/2022 Partial Approval WILLIAM MICHALAK
Underground Mechanical 4/7/2022 Approved WILLIAM MICHALAK
Final 5/27/2022 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 5/27/2022 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 5/27/2022 Not Ready for Inspection WILLIAM MICHALAK
Final 6/2/2022 Corrections Issued WILLIAM MICHALAK
Green Building Final 6/2/2022 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 6/2/2022 Approved WILLIAM MICHALAK
Final 7/27/2022 Corrections Issued WILLIAM MICHALAK
Final 8/5/2022 Conditional Approval WILLIAM MICHALAK
Final 5/30/2024 Not Ready for Inspection WILLIAM MICHALAK
Service/Power Release 5/30/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 9/9/2025 OK to Issue CofO WILLIAM MICHALAK