2129 W QUEENSBOROUGH LANE 90077

Certificate Information: 2129 W QUEENSBOROUGH LANE 90077

Application / Permit
20014-10000-04333
Plan Check / Job No.
B20LA18261
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL REAR OF SFD TO INVOLVE THE RECONFIGURATION OF FAMILY AND LIVING ROOM ON 1ST FLOOR AND MASTER BEDROOM ON 2ND FLOOR. RAISING THE FINISH FLOOR OF THE LIVING AND FAMILY ROOM BY APPROX 6" TO BE LEVEL WITH THE MAIN STAIR LOBBY AND KITCHEN ELEVATION LEVEL. ADDING A BEDROOM (BEDROOM 5) WITHIN EXISTING BLDG ENVELOPE ON 2ND FLOOR. MINOR INTERIOR WALL CHANGES AND RELOCATION. NEW EXTERIOR DOORS AND WINDOWS AND ROOF REPAIR
Permit Issued
Issued on 2/23/2021
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 FARSHAD ALIMOHAMADI
Corrections Issued 10/20/2020 FARSHAD ALIMOHAMADI
Quality Review Completed 10/27/2020 STANLEY RAAP
Building Plans Picked Up 10/30/2020 APPLICANT
Applicant returned to address corrections 2/16/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 2/16/2021 FARSHAD ALIMOHAMADI
Issued 2/23/2021 APPLICANT
CofO in Progress 3/2/2023 CARLOS MATAMOROS
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Tract Map conditions Cleared 11/13/2020 RICHARD REASER
ZA Case Cleared 11/13/2020 RICHARD REASER
ZA Case Cleared 11/13/2020 RICHARD REASER
ZA Case Cleared 11/13/2020 RICHARD REASER
Roof/Waste drainage to street Cleared 11/17/2020 ANTHONY MAINEZ
Sewer availability Cleared 11/17/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/18/2020 ANTHONY MAINEZ

Contact Information

Architect Ivanov,, Pavel Ivanov; Lic. No.: C24047 1509 N CRESCENT HEIGHTS BLVD #6      LOS ANGELES, CA 90046
Contractor Adco Roofing Inc; Lic. No.: 560144-B 5743 CAHUENGA BLVD      NORTH HOLLYWOOD, CA 91610
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/23/2021 Approved CARLOS MATAMOROS
Pre-Inspection 4/15/2021 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 5/13/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 5/13/2021 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Approved CARLOS MATAMOROS
Underground Mechanical 9/9/2021 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 9/29/2021 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 9/29/2021 Approved CARLOS MATAMOROS
Wood Frame 9/29/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 10/4/2021 Corrections Issued CARLOS MATAMOROS
Deputy Wood Construction 10/8/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 10/8/2021 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 10/27/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 10/27/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 10/27/2021 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 10/27/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 11/3/2021 Approved CARLOS MATAMOROS
HVAC-Rough 11/3/2021 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 11/3/2021 Corrections Issued CARLOS MATAMOROS
Wood Frame 11/3/2021 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 11/29/2021 Approved CARLOS MATAMOROS
Green Building Rough 11/29/2021 Approved CARLOS MATAMOROS
HVAC-Rough 11/29/2021 Approved CARLOS MATAMOROS
MERV13>=Rough 11/29/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 11/29/2021 Approved CARLOS MATAMOROS
Insulation 12/7/2021 Approved CARLOS MATAMOROS
Drywall Nailing 12/22/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 1/14/2022 Partial Approval CARLOS MATAMOROS
Service/Power Release 8/30/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 11/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Service/Power Release 11/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Service/Power Release 11/10/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 3/1/2023 Conditional Approval CARLOS MATAMOROS
Final 3/1/2023 OK to Issue CofO CARLOS MATAMOROS
Footing/Foundation/Slab 3/1/2023 Approved CARLOS MATAMOROS
Green Building Final 3/1/2023 Approved CARLOS MATAMOROS
HVAC-Final 3/1/2023 Approved CARLOS MATAMOROS
MERV13>=Final 3/1/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 3/1/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 3/1/2023 Approved CARLOS MATAMOROS