4939 N QUEEN FLORENCE LANE 91364

Certificate Information: 4939 N QUEEN FLORENCE LANE 91364

Application / Permit
20014-10000-04312
Plan Check / Job No.
B20LA18176
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO (E) 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
Issued on 8/10/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 DANIEL YIP
Corrections Issued 12/24/2020 DANIEL YIP
Quality Review Completed 1/7/2021 ALLEN MANALANSAN
Applicant returned to address corrections 1/11/2021 DANIEL YIP
Applicant returned to address corrections 4/1/2021 DANIEL YIP
Applicant returned to address corrections 5/13/2021 DANIEL YIP
Applicant returned to address corrections 5/21/2021 DANIEL YIP
Applicant returned to address corrections 6/8/2021 DANIEL YIP
Plan Check Approved 7/15/2021 DANIEL YIP
Issued 8/10/2021 APPLICANT
Building Plans Picked Up 8/11/2021 APPLICANT

Permit Application Clearance Information

ZI Cleared 2/1/2021 ANACANY HURTADO
Address approval Cleared 2/4/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/4/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/4/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/4/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/4/2021 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/4/2021 LEE GUILBEAUX
Sewer availability Cleared 2/24/2021 LEE GUILBEAUX
Excavation more than 5-ft deep Cleared 3/24/2021 CALOSHA APPROVED
GPI Written Notices Cleared 4/1/2021 DANIEL YIP
Grading Pre-Inspection Cleared 4/1/2021 DANIEL YIP
Excavation more than 5-ft deep Cleared 4/5/2021 CALOSHA APPROVED
Hydrant and Access approval Cleared 4/12/2021 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 5/19/2021 ADRIAN CASTRO
Low Impact Development Cleared 6/23/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/6/2021 LEE GUILBEAUX
Hold Cleared 5/20/2022 JASON SHEETS

Contact Information

Architect Herrero,, Andre; Lic. No.: C38434 6253 HOLLY MONT DR      LOS ANGELES, CA 90068
Architect Womack, & Hampton Architects Llc; Lic. No.: BUS3815 4311 OAK LAWN AVENUE SUITE 50      DALLAS, TX 75219
Contractor Owner-Builder       ,
Engineer Aoanan,, Virgilio Cendana; Lic. No.: C36079 1041 S GARFIELD AVE STE #210      ALHAMBRA, CA 91801
Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/26/2022 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 10/5/2022 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 10/7/2022 Approved SEAN WIRCH
Footing/Foundation/Slab 12/29/2022 Approved PETER FOLLING
PLUMBING-Rough 3/12/2024 Approved GEVORK IPCHYAN
Underground Mechanical 3/12/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 10/23/2024 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 10/23/2024 Not Ready for Inspection JOHN HAYES
HVAC-Rough 10/23/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/23/2024 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 12/23/2024 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 12/23/2024 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 12/23/2024 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 12/26/2024 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 12/27/2024 Partial Approval JOHN HAYES
ELECTRICAL-Rough 12/27/2024 Approved JOHN HAYES
Green Building Rough 12/27/2024 Not Ready for Inspection JOHN HAYES
HVAC-Rough 12/27/2024 Approved JOHN HAYES
PLUMBING-Rough 12/27/2024 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 12/27/2024 Approved JOHN HAYES
Verify Sprinkler Sign Off 12/27/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 4/18/2025 Approved JOHN HAYES
Green Building Rough 4/18/2025 Approved JOHN HAYES
Interior/Exterior Lathing 4/18/2025 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 4/18/2025 Approved JOHN HAYES
Shower Pan 4/18/2025 Approved JOHN HAYES
Insulation 6/6/2025 Conditional Approval JOHN COLEMAN
Drywall Nailing 7/24/2025 Approved JOHN HAYES
Interior/Exterior Lathing 7/24/2025 Approved JOHN HAYES