3859 N SHERWOOD PL 91423

Certificate Information: 3859 N SHERWOOD PL 91423

Application / Permit
20014-10000-04298
Plan Check / Job No.
B20LA18099
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD AND ADDITION TO BASEMENT. ADD NEW ROOFTOP DECK. REPAIR FIRE DAMAGE LUMBER SAME SIZE AND LOCATION. "Comply with Department Order effective date 05/11/2018."
Permit Issued
Issued on 4/23/2022
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 CRYSTEL MAALOUF
Corrections Issued 1/5/2021 CRYSTEL MAALOUF
Quality Review Completed 2/5/2021 TU HUA
Building Plans Picked Up 2/9/2021 APPLICANT
Applicant returned to address corrections 4/23/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/18/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 7/22/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 11/30/2021 CRYSTEL MAALOUF
Plan Check Approved 2/16/2022 CRYSTEL MAALOUF
Issued 4/23/2022 APPLICANT
CofO in Progress 9/25/2024 MISAEL ESPARZA
CofO Issued 10/1/2024 DANIEL ORRANTE
Permit Finaled 10/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/30/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 12/30/2020 ADRIAN CASTRO
Sewer availability Cleared 12/30/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/26/2021 ADRIAN CASTRO
Low Impact Development Cleared 4/1/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 4/8/2021 GABRIEL ROBLES
GPI Written Notices Cleared 2/16/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 2/16/2022 CRYSTEL MAALOUF

Contact Information

Contractor Performance Air Conditioning; Lic. No.: 1060610-B 26470 RUETHER AVE STE 108      SANTA CLARITA, CA 91350
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2022 Partial Inspection MISAEL ESPARZA
Pre-Inspection 5/9/2022 Partial Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 6/22/2022 Partial Approval MATT KELLERMAN
Deputy Drilled-In Anchors 7/21/2022 Conditional Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 8/1/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 10/14/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval MISAEL ESPARZA
Green Building Rough 10/14/2022 Not Ready for Inspection MISAEL ESPARZA
Structural Steel Frame 10/14/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 10/24/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Partial Approval MISAEL ESPARZA
Green Building Rough 10/24/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/8/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 11/21/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/21/2022 Partial Approval MISAEL ESPARZA
Deputy Wood Construction 12/20/2022 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 2/6/2023 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 2/6/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/6/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 2/6/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 2/6/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/15/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 3/15/2023 Approved MISAEL ESPARZA
Green Building Rough 3/15/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 3/15/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/15/2023 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/3/2023 Partial Approval DAVID MATSON
Shower Pan 4/3/2023 Approved DAVID MATSON
Insulation 4/6/2023 Approved MISAEL ESPARZA
Drywall Nailing 4/28/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/2/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 6/9/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 1/30/2024 Approved MISAEL ESPARZA
Final 1/30/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 1/30/2024 Approved MISAEL ESPARZA
Service/Power Release 1/30/2024 Approved MISAEL ESPARZA
Final 4/11/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/11/2024 Approved MISAEL ESPARZA
Green Building Final 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 4/11/2024 Approved MISAEL ESPARZA
Final 7/25/2024 Corrections Issued JOSE AVILA
Green Building Final 7/25/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Approved JOSE AVILA
Final 9/23/2024 OK to Issue CofO MISAEL ESPARZA