12500 N GLADSTONE AVE #720 91342

Certificate Information: 12500 N GLADSTONE AVE #720 91342

Application / Permit
20014-10000-04293
Plan Check / Job No.
B20LA18064
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
THIS PROJECT IS COMPRISED OF THE REMODEL AND EXPANSION OF AN EXISTING CLEANROOM SPACE WITHIN SPECTROLAB BUILDING 720 AS WELL AS CONSTRUCTION OF A NEW BUNKER FOR GAS STORAGE. THE PROPOSED REMODEL INCLUDES SPACES FOR WAFER FABRICATION PROCESSES, INCLUDING USE OF AN EPSILON 2000 EPITAXY TOOL. THE GAS BUNKER IS PROPOSED ADJACENT TO THE FABRICATION SPACE FOR STORAGE OF THE GASEOUS PROCESS-INPUT MATERIALS. TOTAL FLOOR AREA OF THE COMBINED FABRICATION AND GAS BUNKER SPACES IS APPROXIMATELY 1280 SQFT. THE FABRICATION SPACE, INCLUDING OPERATOR AREA, CONTAINS APPROXIMATELY 1000 SQFT. THE GAS BUNKER IS APPROXIMATELY 280 SQFT. ADDITION (250 SQFT.) AND REMODEL TO (E) COMMERCIAL BUILDING.
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 JOE VO
Green Plans Picked Up 11/5/2020 APPLICANT
Corrections Issued 11/12/2020 JOE VO
Disabled Access Plans Picked Up 11/16/2020 APPLICANT
Quality Review Completed 11/19/2020 MINYE PAK
Applicant returned to address corrections 12/17/2020 JOE VO
Plan Check Approved 3/19/2021 JOE VO
Issued 3/19/2021 APPLICANT
Building Plans Picked Up 3/24/2021 APPLICANT
CofO in Progress 3/14/2023 ANDREW DORSO
Permit Finaled 5/2/2023 JEFFREY DURAN
CofO Issued 5/2/2023 JEFFREY DURAN
Permit Finaled 5/2/2023 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2020 CECILIO NAVARRO
Low Impact Development Cleared 12/19/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/22/2020 CECILIO NAVARRO
Fire Marshal Fire Life Safety Cleared 2/24/2021 ANDREW KO
Hydrant and Access approval Cleared 2/24/2021 MATTHEW CRAIG
Green Code Cleared 3/12/2021 JOE VO
Chemical processes Cleared 3/15/2021 SCAQMD APPROVED
DAS Clearance Cleared 3/18/2021 EDDIE GARIN

Contact Information

Contractor K C S West Inc; Lic. No.: 908480-B 250 EAST 1ST STREET STE 600      LOS ANGELES, CA 90012

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2021 Corrections Issued ANDREW DORSO
Footing/Foundation/Slab 5/24/2021 Not Ready for Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 6/4/2021 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 6/16/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 6/29/2021 Not Ready for Inspection ANDREW DORSO
Masonry Wall/Backfill 6/29/2021 Partial Inspection ANDREW DORSO
Reinforced Masonry Frame 6/29/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 7/22/2021 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 8/2/2021 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Inspection ANDREW DORSO
Insulation 8/4/2021 Partial Inspection ANDREW DORSO
Drywall Nailing 8/10/2021 Partial Inspection ANDREW DORSO
Green Building Rough 8/10/2021 Approved ANDREW DORSO
Drywall Nailing 8/13/2021 Approved ANDREW DORSO
Wood Frame 8/13/2021 Approved ANDREW DORSO
Deputy Drilled-In Anchors 9/20/2021 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 9/20/2021 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 11/10/2022 Approved ANDREW DORSO
Green Building Final 11/10/2022 Approved ANDREW DORSO
Reinforced Concrete Frame 11/10/2022 Approved ANDREW DORSO
Reinforced Masonry Frame 11/10/2022 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Approved ANDREW DORSO
Structural Steel Frame 11/10/2022 Approved ANDREW DORSO
Final 3/14/2023 OK to Issue CofO ANDREW DORSO
Smoke Detectors 3/14/2023 Approved ANDREW DORSO