1769 S CRESCENT HEIGHTS BLVD 90035

Certificate Information: 1769 S CRESCENT HEIGHTS BLVD 90035

Application / Permit
20014-10000-04284
Plan Check / Job No.
B20LA18029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED INTERIOR REMODEL AND ADDITION (16'-4" X 30'-2") AT THE REAR OF (E) SFD
Permit Issued
Issued on 1/28/2021
Issuing Office
Current Status
CofO Issued on 11/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/9/2020 FARSHAD ALIMOHAMADI
Corrections Issued 10/11/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 1/6/2021 SINA KHOSRAVI
Issued 1/28/2021 APPLICANT
Building Plans Picked Up 2/1/2021 APPLICANT
CofO in Progress 9/28/2021 STUART CHAPMAN
Permit Finaled 11/1/2021 DEROLD HAUFF
CofO Issued 11/1/2021 DEROLD HAUFF
Permit Finaled 11/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/14/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/15/2020 WALLIE JONG

Contact Information

Contractor Inspire Concepts Inc; Lic. No.: 1037765-B 1037 SOUTH SHERBOURNE DR      LOS ANGELES, CA 90035
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/3/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 2/3/2021 Partial Approval SCOTT FINNILA
METHANE-Barrier 2/3/2021 Partial Approval SCOTT FINNILA
METHANE-Subgrade 2/3/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 2/5/2021 Approved SCOTT FINNILA
PLUMBING-Rough 2/24/2021 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 2/24/2021 Partial Approval SCOTT FINNILA
Wood Frame 2/24/2021 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 3/11/2021 Partial Approval JOSEPH MCGARRY
Wood Frame 3/11/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/25/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 3/25/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2021 Partial Approval STUART CHAPMAN
Green Building Rough 3/25/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 3/25/2021 Approved STUART CHAPMAN
METHANE-Rough 3/25/2021 Approved STUART CHAPMAN
PLUMBING-Rough 3/25/2021 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 4/5/2021 Approved FREDDIE RIVERA
Green Building Rough 4/5/2021 Approved FREDDIE RIVERA
Insulation 4/5/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 4/5/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/21/2021 Off-Hour Fees Due
Shower Pan 4/21/2021 Off-Hour Fees Due
Drywall Nailing 4/23/2021 Partial Approval SCOTT FINNILA
Insulation 4/23/2021 Off-Hour Fees Due
Interior/Exterior Lathing 4/23/2021 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 4/23/2021 Off-Hour Fees Due
Shower Pan 4/23/2021 Approved SCOTT FINNILA
Shower Pan 4/23/2021 Off-Hour Fees Due
Drywall Nailing 5/1/2021 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 5/1/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 8/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/13/2021 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 8/13/2021 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 8/13/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 8/13/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/13/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 8/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 8/25/2021 Approved KATHRYN BUTTERWORTH
Green Building Final 8/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 8/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Not Required KATHRYN BUTTERWORTH
Final 8/26/2021 Corrections Issued KATHRYN BUTTERWORTH
Gas Test 8/26/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 9/27/2021 Approved STUART CHAPMAN
Final 9/27/2021 OK to Issue CofO STUART CHAPMAN
Green Building Final 9/27/2021 Approved STUART CHAPMAN
PLUMBING-Final 9/27/2021 Approved STUART CHAPMAN