10940 N ORO VISTA AVE 91040

Certificate Information: 10940 N ORO VISTA AVE 91040

Application / Permit
20014-10000-04282
Plan Check / Job No.
B20LA17973
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 12' X 18'-2" FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B). ALL WORK PER WFPP. "Comply with the Department order effective date 10/26/12. Permit will expire 30 days from issuance date."
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 6/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/26/2020 CRISTINA SALAZAR
Corrections Issued 10/27/2020 CRISTINA SALAZAR
Plan Check Approved 3/8/2021 JENNIFER LEE
Building Plans Picked Up 3/22/2021 APPLICANT
Issued 9/1/2021 APPLICANT
CofO Issued 6/2/2025 DAVID JAMES
Permit Finaled 6/2/2025 DAVID JAMES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/5/2021 PATRICK MISCHLICH
Address approval Cleared 2/9/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 2/9/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/19/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/19/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Calderon Rony; Lic. No.: 919443-B 1008 SOUTH CHESTER AVENUE      COMPTON, CA 90221

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/22/2022 Approved JASON BRANNON
Footing/Foundation/Slab 4/22/2022 Approved JASON BRANNON
Underground Mechanical 4/22/2022 Approved JASON BRANNON
BUILDING-Rough-Frame 7/6/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 7/6/2022 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Not Ready for Inspection MATTHEW NELSON
Gas Test 7/6/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 7/6/2022 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 7/6/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 7/6/2022 Not Ready for Inspection MATTHEW NELSON
Rough-Elec/Plmb/HVAC 7/6/2022 Not Ready for Inspection MATTHEW NELSON
Wood Frame 7/6/2022 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 7/7/2022 Approved EMIL ALEXANDRIAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Approved EMIL ALEXANDRIAN
Green Building Rough 7/7/2022 Approved EMIL ALEXANDRIAN
Rough-Elec/Plmb/HVAC 7/7/2022 Approved EMIL ALEXANDRIAN
Drywall Nailing 8/9/2022 Not Ready for Inspection MATTHEW NELSON
Insulation 8/9/2022 Not Ready for Inspection MATTHEW NELSON
Drywall Nailing 8/10/2022 Approved JASON BRANNON
Insulation 8/10/2022 Approved JASON BRANNON
ELECTRICAL-Final 10/31/2022 Approved EMIL ALEXANDRIAN
Final 10/31/2022 Corrections Issued EMIL ALEXANDRIAN
Gas Test 10/31/2022 Approved EMIL ALEXANDRIAN
Green Building Final 10/31/2022 Approved EMIL ALEXANDRIAN
PLUMBING-Final 10/31/2022 Approved EMIL ALEXANDRIAN
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready EMIL ALEXANDRIAN
Smoke Detectors 10/31/2022 Approved EMIL ALEXANDRIAN
Final 1/13/2025 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Not Ready WILLIAM WREN
Final 4/4/2025 Corrections Issued MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Not Ready MARIO CUEVAS
Final 4/8/2025 Conditional Approval MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved MARIO CUEVAS