320 N GOWER ST 90004

Certificate Information: 320 N GOWER ST 90004

Application / Permit
20014-10000-04259
Plan Check / Job No.
B20LA17911
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EXISTING SFD. 1 of 2
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
CofO Issued on 2/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 CRYSTEL MAALOUF
Corrections Issued 11/12/2020 CRYSTEL MAALOUF
Quality Review Completed 11/23/2020 WING SUEN
Building Plans Picked Up 12/2/2020 APPLICANT
Applicant returned to address corrections 4/16/2021 CRYSTEL MAALOUF
Plan Check Approved 5/7/2021 CRYSTEL MAALOUF
Issued 6/7/2021 APPLICANT
CofO in Progress 2/23/2023 ALIZAH MAYAGOITIA
No Progress 2/23/2023 SCOTT FINNILA
CofO in Progress 2/24/2023 SCOTT FINNILA
Permit Finaled 2/26/2023 DEROLD HAUFF
CofO Issued 2/26/2023 DEROLD HAUFF
Permit Finaled 2/26/2023 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 12/4/2020 MAXFIELD VERMY
CPC Cleared 12/4/2020 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 12/9/2020 RENZ SORIANO
Sewer availability Cleared 12/9/2020 RENZ SORIANO
Low Impact Development Cleared 4/7/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 4/9/2021 ROSA SILVA

Contact Information

Contractor Goliath Construction; Lic. No.: 1056541-B 6914 RADFORD AVE      NORTH HOLLYWOOD, CA 91605
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/14/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 6/14/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 6/14/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 6/14/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
Underground Mechanical 6/24/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 6/28/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval CHARLES BOGHOSKHAN
Excavation/Setback/Form/Re-Bar 7/22/2021 Approved CHRIS CHRISTENSEN
Special/Order Compliance 7/22/2021 Approved CHRIS CHRISTENSEN
Pre-Inspection 8/25/2021 Approved CHRIS CHRISTENSEN
Sewer 8/25/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 8/25/2021 Approved CHRIS CHRISTENSEN
Pre-Inspection 4/4/2022 Conditional Approval SHAVONNE ESPINOZA
HVAC-Rough 4/29/2022 Partial Approval SHAVONNE ESPINOZA
PLUMBING-Rough 4/29/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 5/4/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 5/4/2022 Approved SHAVONNE ESPINOZA
Deputy Wood Construction 5/6/2022 Approved SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Approved SHAVONNE ESPINOZA
Wood Frame 5/11/2022 Corrections Issued SHAVONNE ESPINOZA
BUILDING-Rough-Frame 5/19/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Rough 5/19/2022 Not Ready for Inspection SHAVONNE ESPINOZA
METHANE-Rough 5/19/2022 Approved SHAVONNE ESPINOZA
Wood Frame 5/19/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Rough 5/26/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 5/26/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 6/1/2022 Approved SHAVONNE ESPINOZA
HVAC-Rough 6/1/2022 Not Ready for Inspection SHAVONNE ESPINOZA
HVAC-Rough 6/7/2022 Approved SHAVONNE ESPINOZA
Insulation 6/7/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 6/7/2022 Approved SHAVONNE ESPINOZA
Drywall Nailing 7/8/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 7/8/2022 Approved JEFFREY MEAD
Shower Pan 7/8/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 12/29/2022 Corrections Issued JEFFREY MEAD
Gas Test 12/29/2022 Approved JEFFREY MEAD
PLUMBING-Final 12/29/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved JEFFREY MEAD
Service/Power Release 12/29/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 2/15/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/15/2023 Approved ALIZAH MAYAGOITIA
Final 2/15/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 2/15/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 2/15/2023 Approved ALIZAH MAYAGOITIA
Smoke Detectors 2/15/2023 Approved ALIZAH MAYAGOITIA
Final 2/22/2023 OK to Issue CofO ALIZAH MAYAGOITIA
HVAC-Final 2/22/2023 Approved ALIZAH MAYAGOITIA