5917 E FAYETTE ST 90042

Certificate Information: 5917 E FAYETTE ST 90042

Application / Permit
20014-10000-04258
Plan Check / Job No.
B20LA17902
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New addition (81sqft) and house and interior remodel (remove of non bearing walls and bearing, remove and replace finished, windows, electrical outlet and plumbing fixture) of (E) s.f.d, Structural alteration per Engineer design
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 4/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/7/2020 RAHEL BEYENE
Corrections Issued 10/14/2020 RAHEL BEYENE
Applicant returned to address corrections 12/9/2020 JESSE JIMENEZ
Applicant returned to address corrections 2/1/2021 GEORGE ALVAREZ
Applicant returned to address corrections 3/24/2021 JESSE JIMENEZ
Plan Check Approved 6/25/2021 FERNANDO FLORES
Building Plans Picked Up 6/29/2021 APPLICANT
Issued 12/2/2021 APPLICANT
CofO in Progress 3/21/2023 CRAIG VAUGHAN
CofO in Progress 3/21/2023 CRAIG VAUGHAN
Permit Finaled 4/22/2023 DEROLD HAUFF
CofO Issued 4/22/2023 DEROLD HAUFF
Permit Finaled 4/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/26/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 10/26/2020 RENZ SORIANO
Sewer availability Cleared 10/26/2020 RENZ SORIANO
Grading Pre-Inspection Cleared 12/9/2020 RAHEL BEYENE

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Av Design Build Construction; Lic. No.: 1033230-B 4654 E AVE S UNIT B116      PALMDALE, CA 93552
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 3/29/2022 Partial Approval SCOTT FINNILA
Green Building Rough 3/29/2022 Not Ready for Inspection SCOTT FINNILA
Underground Mechanical 3/29/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/26/2022 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 5/26/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 5/26/2022 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 7/1/2022 Not Ready for Inspection RUBEN SALAS
Green Building Rough 7/1/2022 Not Ready for Inspection RUBEN SALAS
Wood Frame 7/1/2022 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 7/13/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/13/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 8/24/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 8/24/2022 Approved CRAIG VAUGHAN
Green Building Rough 8/24/2022 Approved CRAIG VAUGHAN
HVAC-Rough 8/24/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 8/24/2022 Corrections Issued CRAIG VAUGHAN
Wood Frame 8/24/2022 Approved CRAIG VAUGHAN
Insulation 8/29/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/29/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 8/29/2022 Approved KATHRYN BUTTERWORTH
Drywall Nailing 9/8/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/8/2022 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 9/16/2022 Approved AMY COLIN
Service/Power Release 11/10/2022 No Access for Inspection KATHRYN BUTTERWORTH
Service/Power Release 12/5/2022 Approved SCOTT FINNILA
ELECTRICAL-Final 1/25/2023 Approved CRAIG VAUGHAN
Final 1/25/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 1/25/2023 Approved CRAIG VAUGHAN
HVAC-Final 1/25/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 1/25/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 1/25/2023 Approved CRAIG VAUGHAN
Final 2/3/2023 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved CRAIG VAUGHAN
Final 3/17/2023 OK to Issue CofO KATHRYN BUTTERWORTH