1738 1/2 W 59TH PL 90047
Certificate Information: 1738 1/2 W 59TH PL 90047
- Application / Permit
- 20014-10000-04245
- Plan Check / Job No.
- B20LA17855
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADUs. Convert existing garage into ADU per ordinance 1-story
- Permit Issued
- Issued on 5/12/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | CARLOS MONTES |
| Corrections Issued | 12/30/2020 | CARLOS MONTES |
| Quality Review Completed | 1/14/2021 | TU HUA |
| Plan Check Approved | 5/3/2021 | CARLOS MONTES |
| Issued | 5/12/2021 | APPLICANT |
| CofO in Progress | 5/12/2022 | ENRIQUE MIRELES |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 12/29/2020 | JASON SHEETS |
| Address approval | Cleared | 2/2/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/3/2021 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/27/2021 | Conditional Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 9/30/2021 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/14/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 11/8/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/21/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 1/21/2022 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 1/21/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/4/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/4/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/4/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Approved | FREDDIE RIVERA |
| Insulation | 2/25/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 3/15/2022 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 3/15/2022 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 3/22/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/29/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 4/29/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/29/2022 | Approved | ANTHONY EGSON |
| Final | 5/11/2022 | OK to Issue CofO | ENRIQUE MIRELES |