10507 N WILSEY AVE 91042

Certificate Information: 10507 N WILSEY AVE 91042

Application / Permit
20014-10000-04243
Plan Check / Job No.
B20LA17851
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION OF (E) GARAGE & ADDITION FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (d)
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 LAMAR DAVIS
Corrections Issued 11/4/2020 LAMAR DAVIS
Quality Review Completed 11/5/2020 TU HUA
Applicant returned to address corrections 1/15/2021 LAMAR DAVIS
Applicant returned to address corrections 1/25/2021 LAMAR DAVIS
Plan Check Approved 2/5/2021 LAMAR DAVIS
Issued 2/10/2021 APPLICANT
CofO in Progress 6/15/2021 MATTHEW NELSON
CofO Issued 9/21/2021 MICHAEL SMITH
Permit Finaled 9/21/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/1/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 12/1/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/1/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/2/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 1/15/2021 TIMOTHY POWELL
Miscellaneous Cleared 1/25/2021 LAMAR DAVIS

Contact Information

Contractor L P Design & Construction; Lic. No.: 901296-B 507 N MCPHERRIN AVE      MONTEREY PARK, CA 91754

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2021 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 2/24/2021 Approved MATTHEW NELSON
PLUMBING-Rough 2/24/2021 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 3/30/2021 Approved MATTHEW NELSON
Green Building Rough 3/30/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 3/30/2021 Approved MATTHEW NELSON
PLUMBING-Rough 3/30/2021 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 4/12/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 4/12/2021 Approved MATTHEW NELSON
Green Building Rough 4/12/2021 Approved MATTHEW NELSON
PLUMBING-Rough 4/12/2021 Approved MATTHEW NELSON
Insulation 4/16/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/16/2021 Approved MATTHEW NELSON
Drywall Nailing 4/21/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/21/2021 Approved LILIANA PORTILLO
Pre-Inspection 4/21/2021 Approved JESUS RODRIGUEZ
Special/Order Compliance 4/21/2021 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 5/18/2021 Not Ready for Inspection MATTHEW NELSON
Final 5/18/2021 Corrections Issued MATTHEW NELSON
Green Building Final 5/18/2021 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 5/18/2021 Approved MATTHEW NELSON
Final 6/1/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Final 6/1/2021 Not Ready for Inspection MATTHEW NELSON
Final 6/8/2021 Corrections Issued MATTHEW NELSON
Green Building Final 6/8/2021 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 6/15/2021 Approved MATTHEW NELSON
Final 6/15/2021 OK to Issue CofO MATTHEW NELSON
Green Building Final 6/15/2021 Approved MATTHEW NELSON
HVAC-Final 6/15/2021 Approved MATTHEW NELSON
PLUMBING-Final 6/15/2021 Approved MATTHEW NELSON