20648 W CLARENDON ST 91367
Certificate Information: 20648 W CLARENDON ST 91367
- Application / Permit
- 20014-10000-04230
- Plan Check / Job No.
- B20LA17777
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached storage building with 13' x 9' addition into a new Accessory Dwelling unit.
- Permit Issued
- Issued on 5/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | MANUEL MONTUFAR |
| Corrections Issued | 10/26/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 11/2/2020 | RODOLFO ARIAS |
| Applicant returned to address corrections | 5/17/2021 | MANUEL MONTUFAR |
| Plan Check Approved | 5/19/2021 | MANUEL MONTUFAR |
| Issued | 5/19/2021 | APPLICANT |
| CofO in Progress | 4/18/2022 | JEFFREY PARD |
| CofO Issued | 4/22/2022 | JOHN JANSON |
| Permit Finaled | 4/22/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/17/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/18/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 5/17/2021 | MANUEL MONTUFAR |
| Green Code | Cleared | 5/17/2021 | MANUEL MONTUFAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2021 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 6/7/2021 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 7/8/2021 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 7/13/2021 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 7/13/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 7/28/2021 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 8/4/2021 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Partial Approval | HENRY KIM |
| Insulation | 8/4/2021 | Partial Approval | HENRY KIM |
| Pre-Inspection | 8/4/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 9/3/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 9/3/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2021 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 9/3/2021 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 9/3/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 9/23/2021 | Partial Approval | HENRY KIM |
| Sewer | 9/23/2021 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 9/23/2021 | Partial Approval | HENRY KIM |
| Pre-Inspection | 9/24/2021 | Partial Inspection | STEPHANIE SWANSON |
| Sewer | 9/24/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 9/30/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 9/30/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 9/30/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 10/7/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 10/7/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Approved | HENRY KIM |
| Green Building Rough | 10/7/2021 | Approved | HENRY KIM |
| HVAC-Rough | 10/7/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 10/7/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 10/7/2021 | Approved | HENRY KIM |
| Insulation | 10/14/2021 | Conditional Approval | JESUS PINEDA |
| Insulation | 10/22/2021 | Corrections Issued | STEVEN BACK |
| Drywall Nailing | 10/27/2021 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/31/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 3/31/2022 | Corrections Issued | STEVEN BACK |
| Final | 3/31/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 3/31/2022 | Approved | STEVEN BACK |
| HVAC-Final | 3/31/2022 | Corrections Issued | STEVEN BACK |
| MERV13>=Final | 3/31/2022 | Approved | STEVEN BACK |
| MERV13>=Rough | 3/31/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 3/31/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 3/31/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Final | 4/15/2022 | Approved | JEFFREY PARD |
| Final | 4/15/2022 | OK to Issue CofO | JEFFREY PARD |
| HVAC-Final | 4/15/2022 | Approved | JEFFREY PARD |
| PLUMBING-Final | 4/15/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 4/15/2022 | Approved | JEFFREY PARD |