20648 W CLARENDON ST 91367

Certificate Information: 20648 W CLARENDON ST 91367

Application / Permit
20014-10000-04230
Plan Check / Job No.
B20LA17777
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached storage building with 13' x 9' addition into a new Accessory Dwelling unit.
Permit Issued
Issued on 5/19/2021
Issuing Office
Current Status
CofO Issued on 4/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 MANUEL MONTUFAR
Corrections Issued 10/26/2020 MANUEL MONTUFAR
Quality Review Completed 11/2/2020 RODOLFO ARIAS
Applicant returned to address corrections 5/17/2021 MANUEL MONTUFAR
Plan Check Approved 5/19/2021 MANUEL MONTUFAR
Issued 5/19/2021 APPLICANT
CofO in Progress 4/18/2022 JEFFREY PARD
CofO Issued 4/22/2022 JOHN JANSON
Permit Finaled 4/22/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/17/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 11/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/18/2020 ADRIAN CASTRO
Sewer availability Cleared 11/18/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/17/2021 MANUEL MONTUFAR
Green Code Cleared 5/17/2021 MANUEL MONTUFAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2021 Approved HENRY KIM
Footing/Foundation/Slab 6/7/2021 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 7/8/2021 Conditional Approval HENRY KIM
Footing/Foundation/Slab 7/13/2021 Corrections Issued HENRY KIM
Special/Order Compliance 7/13/2021 Partial Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/28/2021 Approved PETER FOLLING
BUILDING-Rough-Frame 8/4/2021 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/4/2021 Partial Approval HENRY KIM
Insulation 8/4/2021 Partial Approval HENRY KIM
Pre-Inspection 8/4/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 9/3/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 9/3/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Corrections Issued HENRY KIM
HVAC-Rough 9/3/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 9/3/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 9/23/2021 Partial Approval HENRY KIM
Sewer 9/23/2021 Corrections Issued HENRY KIM
Underground Mechanical 9/23/2021 Partial Approval HENRY KIM
Pre-Inspection 9/24/2021 Partial Inspection STEPHANIE SWANSON
Sewer 9/24/2021 Approved HENRY KIM
BUILDING-Rough-Frame 9/30/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 9/30/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 9/30/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 10/7/2021 Partial Approval HENRY KIM
ELECTRICAL-Rough 10/7/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Approved HENRY KIM
Green Building Rough 10/7/2021 Approved HENRY KIM
HVAC-Rough 10/7/2021 Approved HENRY KIM
Interior/Exterior Lathing 10/7/2021 Approved HENRY KIM
PLUMBING-Rough 10/7/2021 Approved HENRY KIM
Insulation 10/14/2021 Conditional Approval JESUS PINEDA
Insulation 10/22/2021 Corrections Issued STEVEN BACK
Drywall Nailing 10/27/2021 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/31/2022 Approved STEVEN BACK
ELECTRICAL-Final 3/31/2022 Corrections Issued STEVEN BACK
Final 3/31/2022 Corrections Issued STEVEN BACK
Green Building Final 3/31/2022 Approved STEVEN BACK
HVAC-Final 3/31/2022 Corrections Issued STEVEN BACK
MERV13>=Final 3/31/2022 Approved STEVEN BACK
MERV13>=Rough 3/31/2022 Approved STEVEN BACK
PLUMBING-Final 3/31/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 3/31/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 3/31/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Final 4/15/2022 Approved JEFFREY PARD
Final 4/15/2022 OK to Issue CofO JEFFREY PARD
HVAC-Final 4/15/2022 Approved JEFFREY PARD
PLUMBING-Final 4/15/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 4/15/2022 Approved JEFFREY PARD