539 N CHEROKEE AVE 90004

Certificate Information: 539 N CHEROKEE AVE 90004

Application / Permit
20014-10000-04211
Plan Check / Job No.
B20LA17696
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU AND ADD 150 SF. PER GCS 65852.2(e)(1) AND LAMC 12.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 12/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/7/2020 ADAM HEGAZI
Corrections Issued 10/8/2020 ADAM HEGAZI
Building Plans Picked Up 10/9/2020 APPLICANT
Applicant returned to address corrections 4/16/2021 LUKE GONZALES
Plan Check Approved 4/19/2021 LUKE GONZALES
Issued 4/22/2021 APPLICANT
CofO in Progress 11/19/2022 JOAQUIN GREENOUGH
Permit Finaled 12/6/2022 DEROLD HAUFF
CofO Issued 12/6/2022 DEROLD HAUFF
Permit Finaled 12/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/16/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/16/2020 CECILIO NAVARRO
Sewer availability Cleared 10/20/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/21/2021 CECILIO NAVARRO
Construction within easement Cleared 1/28/2021 WALTER RAMIREZ
HPOZ Cleared 4/8/2021 SUKI GERSHENHORN

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Handcrafted Construction Inc; Lic. No.: 841160-B 5408 SEPULVEDA BLVD      CULVER CITY, CA 90230
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/20/2021 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/23/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/22/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 10/8/2021 Partial Approval DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 10/22/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 2/2/2022 Conditional Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 2/2/2022 Corrections Issued BRIAN SULLIVAN
Insulation 2/25/2022 Approved BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 2/25/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/9/2022 Partial Approval RAUL BARAJAS
Drywall Nailing 3/16/2022 Approved RUBEN SALAS
Green Building Rough 3/16/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 4/13/2022 Partial Approval BRIAN SULLIVAN
Shower Pan 4/13/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 7/11/2022 Approved RUBEN SALAS
BUILDING-Rough-Frame 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Gas Test 8/29/2022 Approved JOAQUIN GREENOUGH
Green Building Final 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Final 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 8/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/8/2022 Approved JOAQUIN GREENOUGH
Final 11/8/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/8/2022 Approved JOAQUIN GREENOUGH
Green Building Final 11/8/2022 Approved JOAQUIN GREENOUGH
METHANE-Barrier 11/8/2022 Approved JOAQUIN GREENOUGH
METHANE-Final 11/8/2022 Approved JOAQUIN GREENOUGH
METHANE-Rough 11/8/2022 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 11/8/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 11/8/2022 Approved JOAQUIN GREENOUGH
Final 11/16/2022 Partial Inspection JOAQUIN GREENOUGH
Final 11/22/2022 OK to Issue CofO JOAQUIN GREENOUGH