539 N CHEROKEE AVE 90004
Certificate Information: 539 N CHEROKEE AVE 90004
- Application / Permit
- 20014-10000-04211
- Plan Check / Job No.
- B20LA17696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU AND ADD 150 SF. PER GCS 65852.2(e)(1) AND LAMC 12.22 A.33(c)(d) AND (g)
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 12/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2020 | ADAM HEGAZI |
| Corrections Issued | 10/8/2020 | ADAM HEGAZI |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Applicant returned to address corrections | 4/16/2021 | LUKE GONZALES |
| Plan Check Approved | 4/19/2021 | LUKE GONZALES |
| Issued | 4/22/2021 | APPLICANT |
| CofO in Progress | 11/19/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/6/2022 | DEROLD HAUFF |
| CofO Issued | 12/6/2022 | DEROLD HAUFF |
| Permit Finaled | 12/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/20/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | CECILIO NAVARRO |
| Construction within easement | Cleared | 1/28/2021 | WALTER RAMIREZ |
| HPOZ | Cleared | 4/8/2021 | SUKI GERSHENHORN |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Handcrafted Construction Inc; Lic. No.: 841160-B | 5408 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/20/2021 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/22/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 10/8/2021 | Partial Approval | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 10/22/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/2/2022 | Conditional Approval | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 2/2/2022 | Corrections Issued | BRIAN SULLIVAN |
| Insulation | 2/25/2022 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 2/25/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/9/2022 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 3/16/2022 | Approved | RUBEN SALAS |
| Green Building Rough | 3/16/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 4/13/2022 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 4/13/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 7/11/2022 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 8/29/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Final | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 11/8/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Final | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 11/16/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Final | 11/22/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |