17807-17809 W COLLINS ST 91316

Certificate Information: 17807-17809 W COLLINS ST 91316

Application / Permit
20014-10000-04186
Plan Check / Job No.
B20LA17567
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) GARAGE AND PART OF SFD TO JR ADU PER GCS 65852.2(e) (l)(A) & 65852.22
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 5/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2020 APPLICANT
Assigned to Plan Check Engineer 9/28/2020 GEORGE ALVAREZ
Corrections Issued 9/28/2020 GEORGE ALVAREZ
Applicant returned to address corrections 10/21/2020 CRISTINA SALAZAR
Applicant returned to address corrections 12/9/2020 AUNG SOE
Plan Check Approved 12/10/2020 AUNG SOE
Issued 12/30/2020 APPLICANT
Building Plans Picked Up 1/7/2021 APPLICANT
CofO in Progress 5/19/2021 STEVEN BACK
CofO Issued 5/20/2021 JOHN JANSON
Permit Finaled 5/20/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/17/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/17/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 11/17/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/17/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Inspire Concepts Inc; Lic. No.: 1037765-B 1037 SOUTH SHERBOURNE DR      LOS ANGELES, CA 90035

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/8/2021 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 1/8/2021 Approved DAVID SCANTLIN
PLUMBING-Rough 1/8/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/20/2021 Partial Approval VINCENT HANLEY
Wood Frame 1/20/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/29/2021 Approved VINCENT HANLEY
Drywall Nailing 1/29/2021 Approved VINCENT HANLEY
Green Building Rough 1/29/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/29/2021 Approved VINCENT HANLEY
MERV13>=Rough 1/29/2021 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 1/29/2021 Approved VINCENT HANLEY
Final 2/23/2021 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 2/23/2021 Approved STEVEN BACK
Green Building Final 2/23/2021 Approved STEVEN BACK
MERV13>=Final 2/23/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 2/23/2021 Approved STEVEN BACK
Final 4/6/2021 Corrections Issued STEVEN BACK
Final 5/19/2021 OK to Issue CofO STEVEN BACK