232 S AVONDALE AVE 90049

Certificate Information: 232 S AVONDALE AVE 90049

Application / Permit
20014-10000-04162
Plan Check / Job No.
B20LA17482
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 STORY ADDITION TO EXISTING 2 STORY SINGLE FAMILY STRUCTURE
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 MAHNAZ NOURHASHEMI
Corrections Issued 10/9/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 10/21/2020 TIEN JEN WANG
Building Plans Picked Up 10/22/2020 APPLICANT
Applicant returned to address corrections 1/13/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 2/18/2021 MAHNAZ NOURHASHEMI
Issued 2/18/2021 APPLICANT
CofO in Progress 12/14/2022 CHRISTOPHER WILSON
CofO in Progress 12/14/2022 CHRISTOPHER WILSON
Permit Finaled 1/18/2023 DANIEL ORRANTE
CofO Issued 1/18/2023 DANIEL ORRANTE
Permit Finaled 1/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/16/2020 BARTON HOLMES
Specific Plan Cleared 12/1/2020 VALERIA CEJA
Low Impact Development Cleared 12/16/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/8/2021 DINAH GARIN
Sewer availability Cleared 2/8/2021 DINAH GARIN

Contact Information

Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049
Engineer Shah,, Kamal Rajendra; Lic. No.: C46200 28611 HASKELL CANYON RD      SANTA CLARITA, CA 91390

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/19/2021 Approved ANDREW NAVE
Footing/Foundation/Slab 4/16/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/30/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/6/2021 Not Ready for Inspection PIERRE VEGA
Excavation/Setback/Form/Re-Bar 5/10/2021 Conditional Approval JOHN KIDWELL
Footing/Foundation/Slab 5/18/2021 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 5/25/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 6/10/2021 Partial Approval JOHN KIDWELL
Green Building Rough 6/10/2021 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 6/10/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval JOHN KIDWELL
HVAC-Rough 10/4/2021 Corrections Issued JOHN KIDWELL
ELECTRICAL-Rough 10/13/2021 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 10/13/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 10/21/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 10/22/2021 Approved ANDREW NAVE
HVAC-Rough 10/26/2021 Not Ready for Inspection JOHN KIDWELL
Wood Frame 10/26/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/28/2021 Partial Approval JOHN KIDWELL
Green Building Rough 10/28/2021 Approved JOHN KIDWELL
HVAC-Rough 10/28/2021 Approved JOHN KIDWELL
Drywall Nailing 12/29/2021 Approved JUAN VALENZUELA
Insulation 12/29/2021 Approved JUAN VALENZUELA
Shower Pan 1/11/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/13/2022 Approved JOHN KIDWELL
Shower Pan 2/2/2022 Approved JOHN KIDWELL
Gas Test 2/25/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 3/4/2022 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 3/18/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 3/31/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 4/7/2022 Partial Approval OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Not Ready JUAN VALENZUELA
Sewer 7/1/2022 Approved JUAN VALENZUELA
Underground Mechanical 7/1/2022 Partial Approval JUAN VALENZUELA
Gas Test 7/19/2022 Corrections Issued CLAYTON GRAHAM
Gas Test 11/2/2022 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 11/23/2022 Partial Inspection JUAN VALENZUELA
Final 11/23/2022 Partial Inspection JUAN VALENZUELA
Gas Test 11/23/2022 Approved JUAN VALENZUELA
Green Building Final 11/23/2022 Partial Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 11/23/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 12/3/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 12/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 12/7/2022 Approved KEVIN SARGSYAN
HVAC-Final 12/7/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 12/9/2022 Approved DAVID FEILER
Final 12/9/2022 Corrections Issued DAVID FEILER
Green Building Final 12/9/2022 Approved DAVID FEILER
PLUMBING-Final 12/9/2022 Corrections Issued DAVID FEILER
Smoke Detectors 12/9/2022 Approved DAVID FEILER
Final 12/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 12/10/2022 Approved CHRISTOPHER WILSON
PLUMBING-Final 12/10/2022 Approved CHRISTOPHER WILSON
Final 12/13/2022 OK to Issue CofO CHRISTOPHER WILSON
Service/Power Release 12/15/2022 Approved MICHAEL PELHAM