8826 N AMESTOY AVE 91325

Certificate Information: 8826 N AMESTOY AVE 91325

Application / Permit
20014-10000-04155
Plan Check / Job No.
B20LA17467
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDTIONS , (N) COVERED FRONT PORCH, AND (N) ATT. PATIO TO THE EXISTING ONE STORY SINGLE FAMILY RESIDENCE. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/26/2021
Issuing Office
Valley
Current Status
Issued on 5/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 TSE MING HUANG
Corrections Issued 10/22/2020 TSE MING HUANG
Applicant returned to address corrections 5/5/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 5/5/2021 APPLICANT
Plan Check Approved 5/11/2021 LUISANGEL VALENZUELA
Issued 5/26/2021 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 12/22/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/23/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/11/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/1/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 4/7/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/13/2021 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval MARK JOHNSON
Underground Mechanical 8/3/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/26/2021 Partial Approval MARK JOHNSON
Underground Mechanical 8/26/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 10/4/2021 Approved MARK JOHNSON
Deputy Steel/Welding 10/12/2021 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 11/17/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 11/17/2021 Conditional Approval MICHAEL TEMPLE
ELECTRICAL-Rough 12/16/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 12/16/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 1/11/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 3/14/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 3/14/2022 Approved RAUL OLAGI
HVAC-Rough 3/14/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 4/20/2022 Partial Approval JAVIER RAMOS JR
Shower Pan 4/20/2022 Approved JAVIER RAMOS JR
Insulation 4/27/2022 Approved JAVIER RAMOS JR
Drywall Nailing 5/3/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 5/3/2022 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 5/27/2022 Approved JAVIER RAMOS JR
Final 10/17/2022 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/17/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/28/2022 Approved JAVIER RAMOS JR
Final 10/28/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 5/4/2023 Corrections Issued JAVIER RAMOS JR