2941 N HUTTON DR 90210
Certificate Information: 2941 N HUTTON DR 90210
- Application / Permit
- 20014-10000-04149
- Plan Check / Job No.
- B20LA17437
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (10.7' X 21.2'),175 SQFT ADDITION TO SINGLE FAMILY DWELLING FOR A FAMILY AND LAUNDRY ROOM WITH REMODEL OF (E) 2-CAR GARAGE TO CREATE A NEW SHOWER FOR THE BATHROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | SINA KHOSRAVI |
| Corrections Issued | 10/1/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/4/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/18/2022 | OMAR GARNICA |
| Applicant returned to address corrections | 6/10/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 7/8/2022 | APPLICANT |
| Applicant returned to address corrections | 11/16/2022 | PETER MOSESIAN |
| Plan Check Approved | 1/13/2023 | PETER MOSESIAN |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 2/5/2024 | BRENDAN LOONEY |
| Permit Finaled | 2/14/2024 | DANIEL ORRANTE |
| CofO Issued | 2/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/21/2020 | LIZZI BEDUYA |
| Roof/Waste drainage to street | Cleared | 7/28/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2021 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 2/4/2022 | SINA KHOSRAVI |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | TRACY TATE |
| Sewer availability | Cleared | 5/16/2022 | CATHERINE ADROVER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Beizai,, Vahid Vic; Lic. No.: C43801 | 1125 EAST BROADWAY 159 GLENDALE, CA 91025 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/20/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 3/20/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/23/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 3/23/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 3/23/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 4/4/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/10/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/13/2023 | Partial Approval | MICHAEL PELHAM |
| Green Building Rough | 4/13/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Drywall Nailing | 4/14/2023 | Partial Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/24/2023 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 4/24/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/27/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/27/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 5/2/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 5/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 5/9/2023 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 5/9/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Shower Pan | 5/12/2023 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | JEREMY TODD |
| Green Building Rough | 5/19/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 6/1/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/5/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 9/12/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 10/3/2023 | Partial Approval | BRENDAN LOONEY |
| HVAC-Final | 10/11/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 10/16/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/23/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 11/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 11/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 11/28/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 11/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 11/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/12/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/15/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 12/15/2023 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Final | 12/15/2023 | Corrections Issued | BRENDAN LOONEY |
| Smoke Detectors | 12/15/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 12/28/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 12/28/2023 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Final | 12/28/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 1/9/2024 | Partial Inspection | BRENDAN LOONEY |
| Final | 2/5/2024 | OK to Issue CofO | BRENDAN LOONEY |