1014-1016 W 84TH PL 90044
Certificate Information: 1014-1016 W 84TH PL 90044
- Application / Permit
- 20014-10000-04147
- Plan Check / Job No.
- B20LA17421
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION AND ADDITION TO (E) ATTACHED GARAGE TO CREATE ADU
- Permit Issued
- Issued on 12/3/2020
- Issuing Office
- Current Status
- CofO Issued on 11/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/10/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/18/2020 | ADAM HEGAZI |
| Plan Check Approved | 12/3/2020 | RICARDO RAMIREZ |
| Issued | 12/3/2020 | APPLICANT |
| Building Plans Picked Up | 12/4/2020 | APPLICANT |
| CofO in Progress | 10/1/2021 | FREDDIE RIVERA |
| Permit Finaled | 11/6/2021 | DEROLD HAUFF |
| CofO Issued | 11/6/2021 | DEROLD HAUFF |
| Permit Finaled | 11/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 10/13/2020 | JASON SHEETS |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2020 | JUAN ASHTON |
| Address approval | Cleared | 11/10/2020 | JUAN ASHTON |
| Highway dedication | Cleared | 11/10/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 11/12/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 11/19/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Inman,, Donald J; Lic. No.: C11888 | 5131 FOX HILLS AVENUE BUENA PARK, CA 90621 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/21/2020 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/23/2020 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 1/7/2021 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 1/11/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/8/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/26/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/26/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/26/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/4/2021 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 3/4/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/4/2021 | Approved | DAVID FEILER |
| Deputy Wood Construction | 3/8/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 3/11/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/11/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/11/2021 | Approved | FREDDIE RIVERA |
| Insulation | 3/17/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/17/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 3/23/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 3/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Not Ready | JOHN KLARIN |
| ELECTRICAL-Final | 9/8/2021 | Approved | JOHN KLARIN |
| Final | 9/8/2021 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 9/8/2021 | Partial Approval | JOHN KLARIN |
| PLUMBING-Final | 9/8/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 9/27/2021 | Approved | FREDDIE RIVERA |
| Final | 9/27/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Final | 9/27/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 9/27/2021 | Approved | FREDDIE RIVERA |
| Service/Power Release | 9/27/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 9/27/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/29/2021 | Approved | FREDDIE RIVERA |
| Final | 9/29/2021 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 9/29/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/29/2021 | SGSOV Approved | FREDDIE RIVERA |