737 E 90TH ST 90002
Certificate Information: 737 E 90TH ST 90002
- Application / Permit
- 20014-10000-04115
- Plan Check / Job No.
- B20LA17274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADDITION TO (E) GARAGE TO BE CONVERTED IN TO AN A.D.U. W/ STORAGE PER STATE LAW.
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | FERNANDO FLORES |
| Corrections Issued | 10/5/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 3/16/2021 | ZAW HAN |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| Applicant returned to address corrections | 9/23/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 8/19/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 11/18/2022 | MINA HABILI |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 11/13/2024 | JOSE MACIAS |
| Permit Finaled | 11/21/2024 | DEROLD HAUFF |
| CofO Issued | 11/21/2024 | DEROLD HAUFF |
| Permit Finaled | 11/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/2/2021 | RIDWAN HARDY |
| Address approval | Cleared | 11/12/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2021 | CINDY QI |
| Sewer availability | Cleared | 8/4/2022 | CINDY QI |
| Low Impact Development | Cleared | 8/9/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/10/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/1/2023 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 6/1/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 6/1/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/3/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/9/2023 | Partial Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/1/2023 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/16/2023 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 10/16/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 10/16/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 10/16/2023 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 10/16/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 10/20/2023 | Partial Inspection | MICHAEL LEWIS |
| Insulation | 10/20/2023 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/20/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 10/25/2023 | Approved | MICHAEL LEWIS |
| Insulation | 10/25/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/25/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 11/7/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/7/2023 | Partial Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | MICHAEL LEWIS |
| Final | 2/26/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 2/26/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 2/26/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 2/26/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 6/20/2024 | No Access for Inspection | MICHAEL LEWIS |
| Green Building Final | 6/20/2024 | No Access for Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Service/Power Release | 6/20/2024 | No Access for Inspection | MICHAEL LEWIS |
| Smoke Detectors | 6/20/2024 | No Access for Inspection | MICHAEL LEWIS |
| Final | 10/1/2024 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 10/1/2024 | Approved | LUIS CASTRO |
| PLUMBING-Final | 10/1/2024 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 10/1/2024 | Approved | LUIS CASTRO |
| Final | 10/11/2024 | Conditional Approval | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | JOSE MACIAS |
| Final | 11/5/2024 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 11/13/2024 | Approved | JOSE MACIAS |