5028 E MONTE VISTA ST 90042
Certificate Information: 5028 E MONTE VISTA ST 90042
- Application / Permit
- 20014-10000-04095
- Plan Check / Job No.
- B20LA17223
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITIONS TO DWELLING AT FRONT AND REAR.
- Permit Issued
- Issued on 2/16/2022
- Issuing Office
- Current Status
- CofO Issued on 11/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | STANLEY RAAP |
| Corrections Issued | 10/15/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 7/17/2021 | TSE MING HUANG |
| Plan Check Approved | 8/25/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 8/26/2021 | APPLICANT |
| Issued | 2/16/2022 | APPLICANT |
| CofO in Progress | 10/26/2023 | AMY COLIN |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
| CofO Issued | 11/17/2023 | DEROLD HAUFF |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/3/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 12/3/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2021 | JUAN ASHTON |
| Specific Plan | Cleared | 2/23/2021 | KEVIN ARUCAN |
| CPC | Cleared | 3/11/2021 | KATIE DEBIASE |
| HPOZ | Cleared | 3/11/2021 | KATIE DEBIASE |
| Specific Plan | Cleared | 7/20/2021 | ADRINEH MELKONIAN |
| ZI | Cleared | 7/20/2021 | ADRINEH MELKONIAN |
Contact Information
| Contractor | H D R Construction; Lic. No.: 923536-B | 21800 VERNE AVENUE HAWAIIAN GARDENS, CA 90716 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2022 | Approved | COREY HUPP |
| PLUMBING-Rough | 2/23/2022 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 3/3/2022 | Partial Approval | COREY HUPP |
| Green Building Rough | 3/3/2022 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | ARTHUR SARGSYAN |
| Wood Frame | 3/24/2022 | Partial Approval | ARTHUR SARGSYAN |
| Rough-Elec/Plmb/HVAC | 12/5/2022 | Corrections Issued | OSVALDO PARAMO |
| Shower Pan | 12/5/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/4/2023 | Approved | AMY COLIN |
| Green Building Rough | 1/4/2023 | Approved | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 1/4/2023 | Approved | AMY COLIN |
| Shower Pan | 1/4/2023 | Approved | AMY COLIN |
| Insulation | 1/30/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 1/30/2023 | Approved | AMY COLIN |
| Drywall Nailing | 5/25/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/13/2023 | Approved | AMY COLIN |
| Final | 10/16/2023 | Corrections Issued | AMY COLIN |
| Green Building Final | 10/16/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 10/16/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 10/23/2023 | Approved | AMY COLIN |
| Final | 10/23/2023 | OK to Issue CofO | AMY COLIN |
| HVAC-Final | 10/23/2023 | Approved | AMY COLIN |
| PLUMBING-Final | 10/23/2023 | Approved | AMY COLIN |