3417 N GLENALBYN DR 90065

Certificate Information: 3417 N GLENALBYN DR 90065

Application / Permit
20014-10000-04094
Plan Check / Job No.
B20LA17221
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION AND INTER REMODEL TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/28/2020
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 DANIEL YIP
Corrections Issued 10/19/2020 DANIEL YIP
Quality Review Completed 10/28/2020 ALLEN MANALANSAN
Building Plans Picked Up 11/6/2020 APPLICANT
Applicant returned to address corrections 12/22/2020 DANIEL YIP
Plan Check Approved 12/28/2020 DANIEL YIP
Issued 12/28/2020 APPLICANT
CofO in Progress 2/12/2022 OSVALDO PARAMO
CofO in Progress 2/12/2022 OSVALDO PARAMO
Permit Finaled 2/17/2022 DEROLD HAUFF
CofO Issued 2/17/2022 DEROLD HAUFF
Permit Finaled 2/17/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/3/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 12/3/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 12/3/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 12/3/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 12/3/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 12/3/2020 THOMAS LANG
GPI Written Notices Cleared 12/22/2020 ALLEN MANALANSAN
Specific Plan Cleared 12/23/2020 NASHYA JENSEN

Contact Information

Contractor Eagle Rock Restoration; Lic. No.: 1025285-B 5464 WAMEDA AVE      LOS ANGELES, CA 90041
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/25/2021 Corrections Issued OSVALDO PARAMO
Green Building Rough 5/25/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 5/29/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 5/29/2021 Partial Approval JUAN VALENZUELA
Wood Frame 5/29/2021 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 6/25/2021 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 6/25/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 6/25/2021 Corrections Issued SCOTT FINNILA
Shower Pan 6/25/2021 Approved SCOTT FINNILA
Wood Frame 6/25/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 7/10/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/10/2021 Approved STUART CHAPMAN
HVAC-Rough 7/10/2021 Approved STUART CHAPMAN
Insulation 7/10/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/10/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 7/10/2021 Approved STUART CHAPMAN
Drywall Nailing 7/17/2021 Approved EUGENE CASSIDY
Green Building Rough 7/17/2021 Approved EUGENE CASSIDY
Final 12/4/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/4/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 12/4/2021 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 12/4/2021 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 12/4/2021 Corrections Issued JOAQUIN GREENOUGH
Final 1/28/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 1/28/2022 Approved OSVALDO PARAMO
Green Building Final 1/28/2022 Approved OSVALDO PARAMO
Smoke Detectors 1/28/2022 Not Ready for Inspection OSVALDO PARAMO
Final 2/8/2022 OK to Issue CofO OSVALDO PARAMO
Smoke Detectors 2/8/2022 Approved OSVALDO PARAMO