2907 N MARSH ST 90039
Certificate Information: 2907 N MARSH ST 90039
- Application / Permit
- 20014-10000-04081
- Plan Check / Job No.
- B20LA17178
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO EXISTING GARAGE TO CONVERT INTO ADU PER- LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2020 | RICARDO RAMIREZ |
| Corrections Issued | 12/5/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 12/11/2020 | APPLICANT |
| Applicant returned to address corrections | 4/24/2021 | FERNANDO FLORES |
| Plan Check Approved | 6/15/2021 | RICARDO RAMIREZ |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 10/7/2022 | THOMAS LOGRASSO |
| Permit Finaled | 2/16/2023 | RONALD MYRICK |
| CofO Issued | 2/16/2023 | RONALD MYRICK |
| Permit Finaled | 2/16/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | JEANIE LAM |
| Sewer availability | Cleared | 1/22/2021 | JEANIE LAM |
| ZI | Cleared | 2/11/2021 | KENTON TRINH |
| Hydrant and Access approval | Cleared | 3/26/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/1/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/8/2021 | THOMAS LANG |
Contact Information
| Contractor | Homeworks Construction & Design; Lic. No.: 841888-B | 9641 RICHEON AVE DOWNEY, CA 90240 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 8/23/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/26/2021 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 8/26/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/28/2021 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 9/28/2021 | Partial Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 9/29/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/1/2021 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 10/1/2021 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/22/2021 | No Access for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/28/2021 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 12/28/2021 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 12/28/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/28/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/24/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 1/24/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 1/24/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 1/24/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/24/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/24/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/28/2022 | Approved | AMY COLIN |
| HVAC-Rough | 1/28/2022 | Approved | AMY COLIN |
| Insulation | 1/28/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 1/28/2022 | Approved | AMY COLIN |
| Drywall Nailing | 2/8/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/8/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 2/15/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 8/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 8/17/2022 | Approved | THOMAS LOGRASSO |
| Final | 10/6/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 10/6/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | THOMAS LOGRASSO |