3675 S WELLINGTON ROAD 90016

Certificate Information: 3675 S WELLINGTON ROAD 90016

Application / Permit
20014-10000-04060
Plan Check / Job No.
B20LA17141
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF AN EXISTING GARAGE INTO AN ACCESSORY DWELLING UNIT WITH IRREGULAR ADDITION
Permit Issued
Issued on 12/19/2020
Issuing Office
Current Status
CofO Issued on 8/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2020 APPLICANT
Assigned to Plan Check Engineer 9/28/2020 FARSHAD ALIMOHAMADI
Corrections Issued 9/28/2020 FARSHAD ALIMOHAMADI
Building Plans Picked Up 10/1/2020 APPLICANT
Plan Check Approved 12/8/2020 RICARDO RAMIREZ
Issued 12/19/2020 APPLICANT
CofO in Progress 8/4/2021 DAVID FEILER
CofO Issued 8/14/2021 DEROLD HAUFF
Permit Finaled 8/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/4/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 11/4/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/5/2020 JEANIE LAM
Sewer availability Cleared 11/5/2020 JEANIE LAM
Construction near power lines Cleared 11/17/2020 RIDWAN HARDY

Contact Information

Architect Yano, Architect; Lic. No.: C35777       ,
Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/15/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 1/21/2021 Partial Approval ROBERT MCDOWELL
PLUMBING-Rough 1/21/2021 Partial Approval ROBERT MCDOWELL
Footing/Foundation/Slab 1/29/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 1/29/2021 Partial Inspection DAVID FEILER
Deputy Drilled-In Anchors 2/1/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 2/2/2021 Partial Approval DAVID FEILER
PLUMBING-Rough 2/2/2021 Partial Approval DAVID FEILER
Sewer 2/2/2021 Approved DAVID FEILER
Deputy Drilled-In Anchors 2/10/2021 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 2/16/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 3/19/2021 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 4/19/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 4/19/2021 Partial Approval DAVID FEILER
Green Building Rough 4/19/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 4/19/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/19/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 5/3/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 5/3/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Approved FREDDIE RIVERA
Green Building Rough 5/3/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/3/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 5/3/2021 Approved FREDDIE RIVERA
Shower Pan 5/3/2021 Approved FREDDIE RIVERA
Insulation 5/6/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 5/18/2021 Approved DAVID FEILER
HVAC-Rough 5/18/2021 Partial Approval DAVID FEILER
ELECTRICAL-Final 7/26/2021 Corrections Issued SABAS ALONSO
HVAC-Final 7/26/2021 Approved SABAS ALONSO
PLUMBING-Final 7/26/2021 Approved SABAS ALONSO
ELECTRICAL-Final 7/28/2021 Corrections Issued DAVID FEILER
Final 7/28/2021 Partial Inspection DAVID FEILER
Green Building Final 7/28/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 7/28/2021 SGSOV Approved DAVID FEILER
Smoke Detectors 7/28/2021 Approved DAVID FEILER
ELECTRICAL-Final 8/4/2021 Approved DAVID FEILER
Final 8/4/2021 OK to Issue CofO DAVID FEILER