5831 N LEMONA AVE 91411
Certificate Information: 5831 N LEMONA AVE 91411
- Application / Permit
- 20014-10000-04054
- Plan Check / Job No.
- B20LA17095
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) BED ROOM ADDITION 15'-6"X24'-6" TO THE REAR OF (E) SFD. CREATE A (N) BATH ROOM
- Permit Issued
- Issued on 11/23/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | RAHEL BEYENE |
| Corrections Issued | 10/1/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 10/26/2020 | STARR CHEN |
| Plan Check Approved | 11/10/2020 | SINA KHOSRAVI |
| Building Plans Picked Up | 11/12/2020 | APPLICANT |
| Issued | 11/23/2020 | APPLICANT |
| CofO in Progress | 4/16/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 10/26/2021 | MICHAEL SMITH |
| CofO Issued | 10/26/2021 | MICHAEL SMITH |
| Permit Finaled | 10/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/15/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Washington Construction & Property Service Co; Lic. No.: 609758-B | 2874 WEST 8TH STREET LOS ANGELES, CA 90005 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2020 | Partial Approval | DAVID MATSON |
| Insulation | 12/30/2020 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 12/30/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/31/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 1/4/2021 | Conditional Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Partial Approval | JOHN HAYES |
| Wood Frame | 1/22/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 2/3/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/3/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/3/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/8/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 2/8/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 2/16/2021 | Approved | DAVID SCANTLIN |
| Insulation | 2/16/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 2/16/2021 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 2/19/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 2/19/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/31/2021 | Approved | MATTHEW NELSON |
| Final | 3/31/2021 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/31/2021 | Approved | MATTHEW NELSON |
| Green Building Final | 3/31/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 3/31/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/31/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/31/2021 | Approved | MATTHEW NELSON |
| Final | 4/15/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Pre-Inspection | 6/29/2021 | Corrections Issued | MICHAEL TEMPLE |